Dokumendiregister | Riigi Tugiteenuste Keskus |
Viit | 11.1-13/24/101 |
Registreeritud | 15.02.2024 |
Sünkroonitud | 31.03.2024 |
Liik | Otsus |
Funktsioon | 11.1 Toetuste arendamine, sertifitseerimine ja järelevalve |
Sari | 11.1-13 Eesti – Läti programmi dokumendid otsused |
Toimik | 11.1-13/2024 |
Juurdepääsupiirang | Avalik |
Juurdepääsupiirang | |
Adressaat | |
Saabumis/saatmisviis | |
Vastutaja | Külli Kaare (Riigi Tugiteenuste Keskus, Peadirektori asetäitjale alluvad osakonnad, Toetuste arendamise osakond, Piiriülese koostöö programmide korraldamise talitus) |
Originaal | Ava uues aknas |
Lõkke 4 / 10122 Tallinn / Estonia / + 372 663 8200 / [email protected] / www.rtk.ee/ Reg. code: 70007340
Valga Vallavalitsus
Puiestee tn 8
Valga linn
68203, Valga maakond
15.02.2024 No 11.1-13/24/101
FINANCIAL CORRECTION DECISION
No 17-1
Tallinn
Project Est-Lat 181 “Renewing and developing Valga-Valka twin town common recreational
area“ (Valga-Valka Recreational Area)
Lead Partner: Valga Municipality Government
Beneficiary: Valga Municipality Government
Based on the compromise agreement concluded on 14 December 2023 between Valga
Municipality Government and the Managing Authority and the Tallinn Administrative Court
decision 3-23-1707 of 18 December 2023, the Managing Authority repeals 25% of the costs of the
contract “Valga Veskijärve tänavavalgustuse ehitus ja rekonstrueerimine“ of the project partner
Valga Municipality Government.
Therefore, and according to the Interreg V-A Estonia-Latvia programme 2014-2020 Programme
Manual and based on the 2014-2020 Structural Assistance Act, adopted by the Parliament of the
Republic of Estonia on 13 June 2018, subsection 6 of the paragraph 54, the Managing Authority
decides:
1. Repeal the decision of the State Shared Service Centre from 3 May 2023 on the Financial
Correction Decision No 17 in so far as the correction of 25% that was made to the costs
related to the public procurement "Construction and reconstruction of the street lighting of
Valga Veskijärve" submitted by AS Valga Vesi in the project Est-Lat181 "Renewing and
developing Valga-Valka twin town common recreational area" in connection with the
failure to provide a performance guarantee and the duration of the manufacturer's
guarantee. For the rest, the financial correction decision No 17 on 3 May 2023 remains
valid.
2. Adopt a new decision declaring 5% of the costs of the contract "Construction and
reconstruction of the street lighting of Valga Veskijärve" ineligible.
Circumstances
Pursuant to point 10.1.1 of the public procurement contract, the Contractor undertakes to deliver
to the Contracting Authority, a bank guarantee as a guarantee for the construction period within
14 days from the date of the conclusion of the contract, and which shall be valid until the
completion of the works and acceptance by the Contracting Authority.
According to the public procurement contract, the performance guarantee letter had to be
submitted no later than 14 days after the conclusion of the contract (21.01.2022), which means no
later than 04.02.2022. The verification of the procurement revealed that there was no guarantee
for the construction period, and the corresponding guarantee letter had not been submitted.
Pursuant to point 10.1.2 of the public procurement contract the Contractor undertakes to hand over
a bank guarantee to the Contracting Authority as a guarantee (from a bank previously accepted by
the Contracting Authority) for the guarantee period, at the latest by the date of signing the act of
acceptance of the work.
The letter of guarantee for the guarantee period has been issued late, as the acceptance of the works
has been signed on 16.05.2022 and the letter of guarantee has been issued only on 04.10.2022. The
Contractor submitted a bank guarantee valid from 04.10.2022 to 16.05.2025 as guarantee for the
guarantee period.
Based on point 7.10 of the public procurement contract, the last payment shall be made by the
Contracting Authority after the final acceptance of the works and the signing of the duly executed
building inspection report, the Contractor being entitled to invoice after the handing-over-
acceptance of the work and the acceptance of the guarantee bond by the Contracting Authority.
As the letter of guarantee was issued on 04.10.2022, therefore the requirement to issue the last
invoice has not been respected, as the last invoice was issued on 16.05.2022 and paid on
26.07.2022.
Point 10.2 of the public procurement contract states that the equipment installed during the works
shall be subject to a valid. period of guarantee laid down by the manufacturer, which, in accordance
with the conditions of the contract, must be at least 60 months. This guarantee period shall start
from the date of acceptance of the works by the contracting entity.
As the installed equipment is covered by a manufacturer's guarantee letter valid 5 years from
04.10.2021, the requirement of the Procurement Contract is not fulfilled, as the guarantee letter
was supposed to be valid from May 2022 to May 2027.
The Managing Authority identified that the parties have not mutually agreed to change the terms
of the contract, but the alternative performance of the contract was a consequence of the
Contracting Authority’s negligence and inattention.
The Tallinn Circuit Court, in its judgment on 4 May 2023, in case 3-21-1711, found that amending
a procurement contract requires the expressed consent of both parties (regardless of its form). The
court stated that the contractor's breach of the contract (failure to provide guarantees in a timely
manner) and the breach of obligations arising from the Public Procurement Act by the Contracting
Authority (failure to verify the timely submission of guarantees) do not imply an agreement
between the parties to amend the procurement contract. The court emphasized that the silence or
inaction of the parties must be a consciously made choice, not an error resulting from insufficient
diligence. According to the Tallinn Circuit Court, the failure to demand guarantees for the
performance period and warranty period from the contractor in a timely manner could constitute a
violation of the contracting authority's obligations under the Public Procurement Act. However, it
did not result in an amendment of the procurement contract.
Therefore, the Managing Authority is of the opinion that the alternative performance of the
procurement contract constitutes a violation of Public Procurement Act § 3.
Based on Article 3 of the Estonian Public Procurement act, when carrying out public procurement,
the Contracting Authority must adhere to the following principles:
when carrying out public procurement, the Contracting Authority must act transparently,
verifiably and proportionately;
the Contracting Authority must treat all persons whose place of residence or seat is in
Estonia, in another Member State of the European Union, in another contracting state of
the European Economic Area or in a country that has joined the Government Procurement
Agreement of the World Trade Organization equally and make certain that all restrictions
and criteria imposed on the persons are proportional, relevant and reasoned in relation to
the purpose of the public procurement;
the Contracting Authority must ensure effective use of competition in public procurement,
ensuring that the participation of a public legal person or a private legal person using public
funds in public procurement does not distort competition due to its use of public funds;
the Contracting Authority must avoid a competition-distorting conflict of interest;
the Contracting Authority must use funds economically and expediently, award the public
contract based on the best price-quality ratio, and carry out the public procurement within
a reasonable time.
In certain cases, the lack of a guarantee period guarantee issued by a bank or other financial
institution or its submission, which does not meet the conditions of the public procurement, is
insignificant and does not lead to the financial correction. This is the case if all the following
conditions are met:
1) despite the guarantee requirement, the contractor has a contractual obligation to liquidate the
defects that appeared during the guarantee period, i.e. the contractor has a contractual debt
guarantee;
2) the existence of an additional guarantee is not important due to the specifics of the procurement
object or from the aspect of fulfilling the guarantee obligations due to risk considerations;
3) the additional guarantee is not large in terms of percentage or money.
Taking into account clauses 10.2 and 10.3 of the procurement contract, the guarantee period
guarantee is an additional guarantee to the contractor's own guarantee, i.e. the contractor has a
contractual debt guarantee. The object of the procurement is standard construction work, which
cannot be considered riskier than usual, in which case a higher probability of realization of the
guarantee period guarantee and, consequently, a greater need for it could be assumed. According
to clause 10.1.2 of the contract, the guarantee for the guarantee period is set at 2% of the contract
price, i.e., €1026.90 (€804 of the actual cost of the contract), which is not large in terms of
percentage or monetary value.
Based on the abovementioned, the Managing Authority considers the deviation from the contract
regarding the provision of the guarantee period as an insignificant change. In so far as the
submission of a guarantee period guarantee that does not meet the requirements must be considered
an insignificant change, the earlier making of the last payment in this case must be considered
irrelevant, as this condition was inherently tied to the submission of the guarantee period
guarantee.
Regarding the non-presentation of the guarantee of the performance time and the guarantee period
of the equipment manufacturer, the Managing Authority is of the opinion that the Contracting
Authority has made the terms of the procurement contract more favourable to the Contractor
compared to what was stipulated in the procurement documents, and that these changes would
have broadened the pool of potential participants in the procurement procedure, because:
if the requirement to provide a guarantee letter during the construction period had not been
mandatory, the tender could have been open to tenderers who did not have the possibility
to provide a letter of guarantee. The Contractor was given an advantage of not having to
bear the cost of the guarantee, which was assumed to be included in the cost of the tender,
and it must therefore be assumed that the Contractor was also partially remunerated in the
event of default obligations;
the Contractor got an advantage because it did not have to renew or extend the
manufacturer's guarantee, and since the guarantee extension or renewal was assumed to be
burdensome for the bidders or associated with additional costs, this condition could
discourage interested parties from participating in the tender. Thus, there was an impact on
the circle of bidders.
Due to the nature of the irregularity, it is not possible to precisely quantify the financial impact
when considering application of the correct rate of this financial correction.
The project partner violated the general principles of Article 3 of the Estonian Public Procurement
Act. The violation is related to fundamental principles, such as transparency, equal treatment, non-
discrimination, and competition, which are crucial for maintaining fairness in public procurement
processes.
Considering that the Managing Authority is not aware whether, due to the infringement, the
outcome of the procurement would have been significantly different, and since the condition
covered by the infringement is not a condition regulating the main obligation of the contract and
it is not affecting the performance of the contract throughout, the Managing Authority is of the
opinion that the financial impact resulting from the infringement can not be substantial, so the 5%
correction is applied as a result of the finding of non-compliance. This correction is likely to
address the departure from the established principles and mitigate the impact of the non-
compliance, as regards the fairness and competitiveness of the procurement process.
Considering that the Managing Authority is not aware that the outcome of the procurement would
have been significantly different due to the infringement, and since the condition covered by the
infringement does not regulate the main obligation of the contract or affect its performance
throughout, the Managing Authority is of the opinion that the financial impact resulting from the
infringement cannot be substantial. Therefore, a 5% correction has been applied due to the finding
of non-compliance. This correction aims to address departing from established principles and
mitigate the impact of non-compliance, as regards the fairness and competitiveness of the
procurement process.
Additionally, the correction may serve as a deterrent, encouraging project partners to exercise
greater diligence in adhering to the principles of the Public Procurement Act to avoid similar
penalties in the future. Regular communication and clarification of expectations between procuring
entities and project partners can contribute to minimizing such errors and ensuring a smoother
procurement process.
The total ineligible costs (EUR):
Expenditu
re budget
line
Total cost
of the
contract
including
VAT
(EUR)
Total
declared
costs
(EUR)
ERDF
support
(EUR)
Self-
financing
(EUR)
Total
ineligible
(EUR)
Ineligible
ERDF
support
(EUR)
Ineligible
self-
financing
(EUR)
Infrastruct
ure and
works
51 346.68 40 200.00 34 170.00 6030.00 2010.00 1708.50 301.50
The ERDF support has already been deducted by the Certifying Authority. This correction does
not lead to any further reduction in the costs of the partner.
Legal basis of the financial correction
1. Structural Assistance Act 2014-2020
According to the Article 54 subsection 6 of the Structural Assistance Act 2014-2020 a financial
correction decision shall be based on the procedure for making a financial correction decision
established in the ETC programme or in the procedure for making a financial correction decision,
established on the basis of subsection 7 of the same section, while pursuant to the ETC programme
the making of the financial correction decision is based on the procedure established nationally in
the states participating in the programme.
2. The Guidelines to Financial Corrections
The Guidelines to Financial Corrections for the Estonia - Latvia Programme 2014-2020 establishes
a range of corrections of up to 5%, 10%, 25% and 100% that are applied to the expenditure of a
contract. They take into account the seriousness of the irregularity and the principle of
proportionality. These rates of corrections are applied when it is not possible to quantify precisely
the financial implications for the contract in question.
3. The Public Procurement Act of Estonia
The Public Procurement Act’s paragraph 3 subsection 1-3 and 5 state that the contracting authority
or the contracting entity ensures effective use of competition in public procurement, whereby the
participation of a public legal person or a private legal person using public funds in public
procurement must not distort competition due to its use of public funds and act transparently,
verifiably and proportionately.
4. The Common Provisions Regulation
According to the Article 143(2) of the Regulation No 1303/2013 of the European Parliament and
of the Council of 17 December 2013, the Member States shall in the first instance be responsible
for investigating irregularities and for making the financial corrections required and pursuing
recoveries. In the case of a systemic irregularity, the Member State shall extend its investigation
to cover all operations potentially affected.
5. Protection of the European Communities financial interests
Article 4(1) of the European Union Council 18 December 1995 Regulation (EC, Euratom) No
2988/95 stipulates that any irregularity shall involve withdrawal of the wrongly obtained
advantage. Point d) of the Article 5(1) of the same regulation stipulates that intentional
irregularities or those caused by negligence may lead to the following administrative penalties:
total or partial removal of an advantage granted by Community rules, even if the operator wrongly
benefited from only a part of that advantage.
According to the Article 160(1) of the Regulation (EU) No 2018/1046 all contracts financed in
whole or in part by the budget shall respect the principles of transparency, proportionality, equal
treatment and non-discrimination and according to the point 2 of the Article 160 all contracts shall
be put out to competition on the broadest possible basis.
6. Programme Manual for the Estonia - Latvia Programme 2014-2020
According to the Estonia - Latvia programme 2014-2020 manual point 5.3.4 each partner
organisation is responsible for ensuring that EU and national public procurement rules are
respected and that all contracts comply with the basic principles of transparency, non-
discrimination and equal treatment as defined in the EC Treaty and the Commission Interpretative
Communication on the Community law applicable to contract awards below the EU thresholds.
7. Programme Manual Annex 6. Guidelines to Financial Corrections
According to the Programme Manual Annex 6. Guidelines to Financial Corrections Chapter 2.3.3
Financial correction in case of irregularity related to non-compliance with the general rules on
procurement when the Estonian partner is a contracting authority for the purposes of the
procurement, when Estonian beneficiary or partner is a contracting authority for the purposes of
the public procurement, and the estimated value of a service, goods or building works is equal to
or in excess of simple procurement threshold has violated the obligation to comply with the general
principles of procurement, the financial correction rate of 5, 10, 25 or 100 percent may be applied
depending on the severity of the violation by using the financial correction principles according to
the EC Guidelines.
8. Subsidy Contract
Article 1 of the Subsidy Contract stipulates that the partners should also follow the EU and national
principles on protection of environment, sustainable development, equal opportunities, non-
discrimination.
Point 2 of the Article 3 of the Subsidy Contract regulates that the Lead Partner and Project Partner
shall implement the project with the requisite care, efficiency, transparency and diligence, in line
with best practice in the field concerned and in compliance with this Contract. For this purpose,
the Lead Partner and Project Partner shall mobilise all the financial, human and material resources
required for full implementation of the project as specified in the approved application.
9. Hearing of opinions and objections of participants in proceedings
According to § 40 (1) of the Administrative Procedure Act, before issuing an administrative act,
the party to the proceedings must be given the opportunity to express their opinion and objections
regarding the matter in written, oral, or any other suitable form. There were no comments from the
leading partner.
DECISION
1. Based on the 2014-2020 Structural Assistance Act, adopted by the Parliament of the Republic
of Estonia on 13 June 2018, and Guidelines to Financial Corrections for the Estonia - Latvia
Programme 2014-2020, the Managing Authority decides to apply:
5% of the costs of the contract “Valga Veskijärve tänavavalgustuse ehitus ja
rekonstrueerimine“ of the project partner Valga Municipality Government are ineligible.
2. Ineligible costs of the project partner Valga Municipality Government are already deducted,
no further deduction of this matter is therefore made.
Appeal of the decision
The present Financial Correction Decision No 17-1 may be appealed in accordance with the Annex
4 to the Programme Manual, which is available on the web-site https://old.estlat.eu/.
Ege Ello
Head of the Managing Authority
Cooperation Programme
Interreg V-A Estonia-Latvia
Grants Development Department
Külli Kaare