Dokumendiregister | Riigi Tugiteenuste Keskus |
Viit | 11.1-12/24/1882-1 |
Registreeritud | 14.08.2024 |
Sünkroonitud | 15.08.2024 |
Liik | Sissetulev kiri |
Funktsioon | 11.1 Toetuste arendamine, sertifitseerimine ja järelevalve |
Sari | 11.1-12 Euroopa majanduspiirkonna ja Norra finantsmehhanismi kirjavahetus 2014-2020 |
Toimik | 11.1-12/2024 |
Juurdepääsupiirang | Avalik |
Juurdepääsupiirang | |
Adressaat | Kliimaministeerium |
Saabumis/saatmisviis | Kliimaministeerium |
Vastutaja | Liina Thalfeldt (Riigi Tugiteenuste Keskus, Peadirektori asetäitjale alluvad osakonnad, Toetuste maksete osakond, Norra ja Euroopa Majanduspiirkonna sertifitseeriv asutus) |
Originaal | Ava uues aknas |
Suur-Ameerika 1 / Tallinn 10122 / 626 2802/ [email protected] / www.kliimaministeerium.ee/
Registrikood 70001231
Karin Viikmaa
Riigi Tugiteenuste Keskus
14.08.2024 nr 4-5/19/53
EE-CLIMATE programmi kümnenda
finantsvahearuande esitamine
Austatud Karin Viikmaa
Esitame Euroopa Majanduspiirkonna Finantsmehhanismist 2014-2021 rahastatava EE-CLIMATE
programmi "Kliimamuutuste leevendamine ja nendega kohanemine" kümnenda
finantsvahearuande
Lugupidamisega
(allkirjastatud digitaalselt)
Tanel Ross
Finantsosakonna juhataja
Lisa: EE-CLIMATE programmi kümnes finantsvahearuanne
Teadmiseks: [email protected], [email protected]
Eleri Seer, 605 0298
1 Version 1.0 as of 13/08/2024 13:33:06 CEST
Interim financial report EEA Financial Mechanisms 2014 – 2021
Interim financial report number 10
Programme summary
Programme operator Ministry of Climate - Estonia
Beneficiary State Estonia
Programme title Climate Change Mitigation and Adaptation
Programme code EE-CLIMATE
Eligible Expenditure € 7,058,823.53
Programme grant rate 85.00 %
Programme grant amount € 6,000,000.00
EEA Grant Amount € 6,000,000.00
Norway Grant Amount € 0.00
Start date of eligibility 10/05/2017
Final date of eligibility 30/04/2025
2 Version 1.0 as of 13/08/2024 13:33:06 CEST
Part A - Statement of actual expenditure incurred
Incurred expenditure - summary
Interim financial report number 10
Start date of incurred expenditure period 01/01/2024
End date of incurred expenditure period 30/06/2024
Previously
incurred
expenditure
Incurred this
period Total to date Total Budget
Available
balance
Eligible
expenditure € 4,144,285.13 € 2,188,902.90 € 6,333,188.03 € 7,058,823.53 € 725,635.50
EEA Grants € 3,522,642.36 € 1,860,567.47 € 5,383,209.83 € 6,000,000.00 € 616,790.17
Co-financing € 621,642.77 € 328,335.43 € 949,978.20 € 1,058,823.53 € 108,845.33
Incurred expenditure - details
Title: Programme management
Previously
incurred
expenditure
Incurred this
period Total to date Budget
Available
balance
Eligible
expenditure € 377,075.16 € 103,932.31 € 481,007.47 € 705,823.53 € 224,816.06
Brief description of actual expenditure incurred
The first half of 2024 projects were ending the implementing stage. All the projects’ activities were completed
by 30.04.2024.
Within Programme Management there were expenditures regarding salary of one PO employee (Jan-June),
organizing CC meeting in Tallinn, final event in Tartu, EE-LV Joint Programme Operator event and also
expenditures participating Czeck EEA Grants seminar.
EIC’s expenditures were related to the approval and transfer of payments to Project Promoters, also
projects’ monitoring and onsite checks and Communication activities.
Eligible expenditures
Eligible expenditure - EUR
€ 103,932.31
Total
€ 103,932.31
Title: Outcome 1: Ecosystem resilience increased (EEA Grants)
Previously
incurred
expenditure
Incurred this
period Total to date Budget
Available
balance
Eligible
expenditure € 465,523.80 € 170,796.74 € 636,320.54 € 800,000.00 € 163,679.46
Brief description of actual expenditure incurred for the outcome
Expenditures incurred were related to Project management costs; participation costs of seminars; pathway
analysis of invasive alien species; Control of invasive alien species; research and analyses of alien species;
methodologies of biological survey (e-DNA); assessment of the biological impact of marine non-indigenous
species; purchase of small equipment; communication costs and; training costs.
3 Version 1.0 as of 13/08/2024 13:33:06 CEST
Eligible expenditures
Project
Eligible
expenditure -
EUR
EE-CLIMATE-0011 € 109,254.55
EE-CLIMATE-0012 € 61,542.19
Total
€ 170,796.74
Title: Outcome 2: Increased ability at the local level to reduce emissions and adapt to a changing
climate (EEA Grants)
Previously
incurred
expenditure
Incurred this
period Total to date Budget
Available
balance
Eligible
expenditure € 2,220,330.90 € 1,568,163.97 € 3,788,494.87 € 3,753,000.00 € -35,494.87
Brief description of actual expenditure incurred for the outcome
Projects’ expenditures in 2024 were related to different construction works (planning, landscaping, planting,
etc); communication costs, workshops, sowing native seeds, planting trees, also project’s final events
(publicity) and project management costs.
Eligible expenditures
Project
Eligible
expenditure -
EUR
EE-CLIMATE-0022 € 177,549.18
EE-CLIMATE-0023 € 154,045.05
EE-CLIMATE-0018 € 351,034.49
EE-CLIMATE-0025 € 319,553.87
EE-CLIMATE-0019 € 81,098.61
EE-CLIMATE-0020 € 67,073.26
EE-CLIMATE-0024 € 120,602.76
EE-CLIMATE-0016 € 146,535.55
EE-CLIMATE-0026 € 150,671.20
Total
€ 1,568,163.97
Title: Outcome 3: Framework for Circular Economy strengthened (EEA Grants)
Previously
incurred
expenditure
Incurred this
period Total to date Budget
Available
balance
Eligible
expenditure € 1,081,355.27 € 346,009.88 € 1,427,365.15 € 1,800,000.00 € 372,634.85
Brief description of actual expenditure incurred for the outcome
Expenditures incurred were related to project management costs, workshops, and meetings; studies;
communication costs; equipment for re-use centers; and study visits.
4 Version 1.0 as of 13/08/2024 13:33:06 CEST
Eligible expenditures
Project
Eligible
expenditure -
EUR
EE-CLIMATE-0013 € 191,703.19
EE-CLIMATE-0014 € 56,667.76
EE-CLIMATE-0015 € 50,393.91
EE-CLIMATE-0017 € 47,245.02
Total
€ 346,009.88
5 Version 1.0 as of 13/08/2024 13:33:06 CEST
Part B - Statement of proposed expenditure
Proposed expenditure - summary
Start date of proposed expenditure period 01/11/2024
End date of proposed expenditure period 30/04/2025
Previous
advance and
interim
payments
Interim
payment this
period
Total to date Budget Available
balance
Eligible
expenditure € 6,790,785.13 € -303,367.10 € 6,487,418.03 € 7,058,823.53 € 571,405.50
EEA Grants € 5,772,167.36 € -257,862.03 € 5,514,305.33 € 6,000,000.00 € 485,694.67
Co-financing € 1,018,617.77 € -45,505.07 € 973,112.70 € 1,058,823.53 € 85,710.83
Title: Programme management
Brief description of activities to be financed
Cooperation activities, exchange of best practices between the Programme Operators and similar entities within
the Beneficiary State and/or Donor States, and/or international organisations. Promotional and information
activities. Compiling final reports of the Programme. Programme evaluation.
Previous
advance and
interim
payments
Interim
payment this
period
Total to date Budget Available
balance
Eligible
expenditure € 560,575.16 € 74,662.31 € 635,237.47 € 705,823.53 € 70,586.06
* For management costs it is not possible to request more than € 635,241.18 of the total amount as 10.00 % is
retained for the programme closure.
Title: Outcome 1: Ecosystem resilience increased (EEA Grants)
Brief description of activities to be financed
All projects are completed as of 09.08.2024, and no disbursements are to be claimed during this period (Nov
2024-Apr 2025).
For period 01.07.2024-31.12.2024 there are some expenditures related to project management costs;
participation costs of seminars; pathway analysis of invasive alien species; control of invasive alien species;
research and analyses of alien species; methodologies of biological survey (e-DNA); assessment of the
biological impact of marine non-indigenous species; purchase of small equipment; communication costs and;
training costs.
Previous
advance and
interim
payments
Interim
payment this
period
Total to date Budget Available
balance
Eligible
expenditure € 782,523.80 € -146,203.26 € 636,320.54 € 800,000.00 € 163,679.46
Title: Outcome 2: Increased ability at the local level to reduce emissions and adapt to a changing
climate (EEA Grants)
Brief description of activities to be financed
For period 01.07.2024-31.12.2024 financing is needed to finalize construction works (i.e. landscaping);
communication costs, also projects’ final events and project management costs.
6 Version 1.0 as of 13/08/2024 13:33:06 CEST
Previous
advance and
interim
payments
Interim
payment
this period
Total to date Budget Available
balance
Eligible
expenditure € 3,720,330.90 € 68,163.97 € 3,788,494.87 € 3,753,000.00 € -35,494.87
Title: Outcome 3: Framework for Circular Economy strengthened (EEA Grants)
Brief description of activities to be financed
For period 01.07.2024-31.12.2024 there are some expenditures related to project management costs, finalizing
project activities (equipment for reuse centers).
Previous
advance and
interim
payments
Interim
payment this
period
Total to date Budget Available
balance
Eligible
expenditure € 1,727,355.27 € -299,990.12 € 1,427,365.15 € 1,800,000.00 € 372,634.85
7 Version 1.0 as of 13/08/2024 13:33:06 CEST
Programme operator Full legal name: Ministry of Climate - Estonia (EE)
Programme operator signature
I certify that I am duly authorised to sign this interim financial report and that the proposed
expenditure described in Part B from which this interim payment is calculated is a realistic
estimate of the expenditure that will actually be required by the Programme in the period
referred to in Part B.
I have thoroughly reviewed the actual expenditure incurred declared in Part A, and co -
financing provided in Part B of this report, and confirm that the information provided is accurate.
I confirm that this Programme is carried out as described in the Programme Agreement and
that the incurred expenditure is correctly represented.
Overall implementation status (including milestones):
The first half of 2024 projects were ending the implementing stage. All the projects’ activities
were completed by 30.04.2024.
Question Answer Comment
Management and control
systems of the Programme
Operator set up fulfilling the
general principles set out in the
Regulation and approved by the
National Focal Point (Art 5.7)
Yes
The setup of management and control
system for the programme started in 2019.
The compliance audit of the management
and control system of the EE-Climate
programme has started in April 2020 and
finished 13 July 2020.
Separate interest-bearing bank
accounts dedicated to the funds
intended for regranting
established and maintained (Art
5.6.1 (m))
Yes Responsibility of CA.
Information and publicity
obligations fulfilled (Art 3.3) Yes
EE-CLIMATE Programme webpage is
operated by the webpage of Ministry of the
Climate. Information about the open calls
can be found on the webpage of
Implementing Agency. Information articles,
press releases etc about opening Call II
were published in media by POIA.
Monitoring and verifications
conducted to ensure quality
and/or regularity of
implementation (Art 5.6.1 (g) and
Art 5.6.2)
Yes
Constant communication via e-mails and
phone calls with project promoters.
Participating in the meetings of steering
committee of pre-defined project.
Annual monitoring of a sample of
projects conducted (Art 5.6.1 (i)) Yes
Project promoters of Call I and pre-defined
project submitted their annual project reports
and these were checked by POIA.
Project-specific statistical data is
entered and up to date in the
reporting database (Art 5.6.1 (s))
Yes Project specific data is entered in reporting
database.
8 Version 1.0 as of 13/08/2024 13:33:06 CEST
Special conditions and
Programme-specific rules set out
in the programme agreement
fulfilled (Art 5.6.1 (x))
N/A There are no programme-specific rules set
out in the programme agreement.
All irregularities, their
investigation and any remedies
taken reported (Art 5.6.1 (v))
Yes All occurred irregularities are reported.
For the Programme Operator
Signed in Tallinn
Tanel Ross
9 Version 1.0 as of 13/08/2024 13:33:06 CEST
Certification of actual expenditure incurred and co-financing Interim financial report number 10
Start date of incurred expenditure period 01/01/2024
End date of incurred expenditure period 30/06/2024
Actual expenditure incurred this period € 2,188,902.90
Start date of proposed expenditure period 01/11/2024
End date of proposed expenditure period 30/04/2025
Co-financing committed to date € 973,112.70
Co-financing for incurred expenditure paid € 949,978.20
The Certifying Authority hereby certifies that:
The Certifying Authority hereby certifies that:
(i) the summary of eligible expenditure submitted by the Programme Operator is in full
conformity with the supporting documents;
(ii) the supporting documents have been examined and found to be authentic, correct and
accurate;
(iii) the summary of eligible expenditure is based on verifiable accounting which is in
compliance with generally accepted accounting principles and methods;
(iv) the summary of eligible expenditure falls within eligible expenditure under the Regulation
for the implementation of the EEA / Norwegian Financial Mechanisms 2014-2021;
(v) the summary of expenditure is incurred as part of the implementation of the Programme in
accordance with the Programme Agreement;
(vi) sufficient audit trail exists;
(vii) co-financing committed to date has been made available;
(viii) co-financing in relation to incurred expenditure has been paid;
(ix) when relevant, that the interest earned at PO account is correct.
For the Certifying Authority
Signed in ................................. on ................
......................................................................
10 Version 1.0 as of 13/08/2024 13:33:06 CEST
Outcomes
Objective: Climate change mitigated and vulnerability to climate change reduced
Outcome 1: Ecosystem resilience increased
Indicator Unit of
measurement Baseline
Achievements
until end of
previous
reporting
period
Achievements until end June
Target Comment Numerator Denominator Value
Number of regions with pressure on indigenous
species
Cumulative
number 20 0 (APR 2023) Reported Annually (APR) 0 -
Number of marine regions with climate
regulation services improved
Cumulative
number 0 1 (APR 2023) Reported Annually (APR) 3 -
Output 1.1: Invasive alien species impact and pathways analysed
Indicator Unit of
measurement Baseline
Achievements
until end of
previous
reporting
period
Achievements until end June
Target Comment Numerator Denominator Value
Number of invasive alien species whose
pathways are analysed
Cumulative
number 0 20 (APR 2023) - - 37 10
University of Tartu examined 27
species (The existing analysis was
updated from 2017 for the
analysis of the income paths of
alien species which included
more species) and University of
Life Sciences 10.
Number of invasive species analysed for impact Cumulative
number 0 10 (APR 2023) - - 14 8
Indicator exceeded with analysis
done by University of Tartu
Output 1.2: Measures to reduce invasive species implemented
Indicator Unit of
measurement Baseline
Achievements
until end of
previous
Achievements until end June
Target Comment Numerator Denominator Value
11 Version 1.0 as of 13/08/2024 13:33:06 CEST
reporting
period
Number of localities where alien species have
been targeted
Cumulative
number 0 20 (APR 2023) - - 20 20 -
Number of invasive species combated Cumulative
number 0 3 (APR 2023) - - 3 4
Number of invasive species
combated Cumulative number 0
3 (APR 2023) - - 3 4 Elodea
nutatallii has not been found in
EST, therefore the target value
will not be achieved
Number of professional staff trained Cumulative
number 0 35 (APR 2023) - - 40 30
Input from 2 alien species
projects
Gender
Female - - 0 - - 0 - -
Male - - 0 - - 0 - -
Not specified - - 35 - - 40 - -
Output 1.3: Restoration of carbon-sequestering marine habitats piloted
Indicator Unit of
measurement Baseline
Achievements
until end of
previous
reporting
period
Achievements until end June
Target Comment Numerator Denominator Value
Number of habitats that sequester and store
blue carbon restored
Cumulative
number 0 1 (APR 2023) - - 1 1 -
Outcome 2: Increased ability at the local level to reduce emissions and adapt to a changing climate
Indicator Unit of
measurement Baseline
Achievements
until end of
previous
reporting
period
Achievements until end June
Target Comment Numerator Denominator Value
Number of people self-reporting increased
awareness on climate adaptation and
mitigation
Cumulative
number 0 0 (APR 2022) Reported 2020, 2022, 2024 10,000 -
12 Version 1.0 as of 13/08/2024 13:33:06 CEST
Number of municipalities supported to come
into compliance with national or EU
mitigation/adaptation strategies
Cumulative
number 0 34 (APR 2023) - - 34 6 -
Output 2.1: Local level climate change mitigation and adaptation plans developed
Indicator Unit of
measurement Baseline
Achievements
until end of
previous
reporting
period
Achievements until end June
Target Comment Numerator Denominator Value
Number of local level energy and climate
change mitigation and adaptation plans
developed
Cumulative
number 0 10 (APR 2023) - - 10 6 -
Output 2.2: Mitigation and adaptation measures implemented
Indicator Unit of
measurement Baseline
Achievements
until end of
previous
reporting
period
Achievements until end June
Target Comment Numerator Denominator Value
Number of climate change mitigation and
adaptation measures implemented
Cumulative
number 0 9 (APR 2023) - - 21 6
9 projects contributed to
achieving this indicator
Output 2.3: Increased public awareness on climate change
Indicator Unit of
measurement Baseline
Achievements
until end of
previous
reporting
period
Achievements until end June
Target Comment Numerator Denominator Value
Number of people reached by general
awareness-raising activities
Cumulative
number 0
17,655 (APR
2023) - - 303,903 10,000
Number of people reached by
general awareness-raising
activities Cumulative number 0
17,655 (APR 2023) - - 303 903
10,000 Call II projects’ input with
all their publication activities
13 Version 1.0 as of 13/08/2024 13:33:06 CEST
Number of schools taking part in climate
change education programmes supported by
the programme.
Cumulative
number 0 0 (APR 2023) - - 94 30 -
Outcome 3: Framework for Circular Economy strengthened
Indicator Unit of
measurement Baseline
Achievements
until end of
previous
reporting
period
Achievements until end June
Target Comment Numerator Denominator Value
Estonian Government is in compliance with the
EU strategy for Circular Economy Binary No
Yes (APR
2023) Reported 'Yes' in 2023 Yes Yes -
Output 3.1: Enhanced capacity on Circular Economy
Indicator Unit of
measurement Baseline
Achievements
until end of
previous
reporting
period
Achievements until end June
Target Comment Numerator Denominator Value
Strategy on Circular Economy completed Binary No Yes (APR
2023) Reported 'Yes' in 2023 Yes Yes -
Number of professionals trained on Circular
Economy
Cumulative
number 0
100 (APR
2023) - - 100 100
Pre-defined project carried out 5
trainings in different regions,
where 100 professionals were
trained
Gender
Female - - 0 - - 0 - -
Male - - 0 - - 0 - -
Not specified - - 100 - - 100 - -
Number of categories for Green Public
Procurement developed
Cumulative
number 0 5 (APR 2023) - - 5 10
10 categories for Green Public
procurement are developed, but
5 of them in frame of project -
electricity, textile (goods and
services),construction of office
buildings, road planning and
14 Version 1.0 as of 13/08/2024 13:33:06 CEST
construction, food products and
services and food vending
machines
Number of people reached by awareness
raising campaigns
Cumulative
number 0
200,000 (APR
2023) - - 200,000 10,000
The media campaign included TV,
radio, social media, outdoor
advertising, screens in public
transportation and it reached at
least 200 000 different people.
Number of schools participating in Green
Schools Competition
Cumulative
number 0 36 (APR 2023) - - 36 30
36 schools registered, 20
submitted their video for the
competition
Output 3.2: Measures for Circular Economy implemented
Indicator Unit of
measurement Baseline
Achievements
until end of
previous
reporting
period
Achievements until end June
Target Comment Numerator Denominator Value
Number of circular economy pilot measures
implemented
Cumulative
number 0 0 (APR 2023) - - 2 4
One project is not yet completed
(final disbursements and reports
are in process). The budget of
the call made it possible to
implement 3 pilot measures.
Bilateral Outcome: Enhanced collaboration between beneficiary and donor state entities involved in the programme
Indicator Unit of
measurement Baseline
Achievements
until end of
previous
reporting
period
Achievements until end June
Target Comment Numerator Denominator Value
Level of trust between cooperating entities in
beneficiary states and donor states Scale 1-7
6.63,
Based
on the
survey
carried
out on
6.94 (APR
2023) Reported Annually (APR)
4.50,
Target is
≥4.5,
and an
increase
on the
-
15 Version 1.0 as of 13/08/2024 13:33:06 CEST
behalf
of the
FMO
baseline
value
Level of satisfaction with the partnerships Scale 1-7
6.61,
Based
on the
survey
carried
out on
behalf
of the
FMO
6.75 (APR
2023) Reported Annually (APR)
4.50,
Target is
≥4.5,
and an
increase
on the
baseline
value
-
Share of cooperating organisations that apply
the knowledge acquired from bilateral
partnerships
Percentage N/A 75.00 % (APR
2023) Reported Annually (APR) 50.00 % -
Bilateral Output 1: Cooperation between beneficiary and donor state entities supported
Indicator Unit of
measurement Baseline
Achievements
until end of
previous
reporting
period
Achievements until end June
Target Comment Numerator Denominator Value
Number of training courses organised by donor
state and beneficiary state entities
Cumulative
number 0 16 (APR 2023) - - 26 10 -
Number of projects involving cooperation with
a donor state partner
Cumulative
number 0 14 (APR 2023) - - 14 5 -