Dokumendiregister | Transpordiamet |
Viit | 8-5/22/22386-1 |
Registreeritud | 04.10.2022 |
Sünkroonitud | 02.12.2024 |
Liik | Sissetulev kiri |
Funktsioon | 8 TEETARISTU EHITAMINE JA REMONTIMINE |
Sari | 8-5 Keskkonnakaitse dokumendid |
Toimik | 8-5/2022 |
Juurdepääsupiirang | Avalik |
Juurdepääsupiirang | |
Adressaat | Keskkonnaministeerium |
Saabumis/saatmisviis | Keskkonnaministeerium |
Vastutaja | Rein Kallas (Transpordiamet, Users, Taristu haldamise teenistus, Projekteerimise osakond, Taristu kooskõlastuste üksus) |
Originaal | Ava uues aknas |
RWE Renewables Sweden AB
Södra Victoria Wind Farm
Consultation document
Gothenburg, 1 July 2022
Ramboll Sweden AB
Box 5343, Vädursgatan 6
SE-402 27 Gothenburg
Tel. +46 (0)10 615 60 00
Södra Victoria Wind Farm Consultation document
Date 1 July 2022
Assignment number 1320059706-002
Issue/Status Final
Lina Sultan Kajsa Palmqvist, Karin Skantze
Claire Hébert,
Oliver Ottvall,
Sofia Elg
Assignment manager Administrator Reviewer
i
Contents
1. Introduction ...........................................................................................1
1.1 Administrative details ................................................................................. 1
1.2 Background .............................................................................................. 1
1.3 Consultation document and consultation process ............................................ 2
2. Legislation and permit processes ............................................................3
2.1 Applicable provisions and delimitation ........................................................... 3
2.2 Environmental Impact Assessment ............................................................... 4
2.3 Review .................................................................................................... 4
3. Activity description .................................................................................5
3.1 Location ................................................................................................... 5
3.2 Design ..................................................................................................... 6
3.3 Technical description .................................................................................. 7
4. Options ................................................................................................ 16
4.1 Main option ............................................................................................ 16
4.2 The zero option ....................................................................................... 16
4.3 Alternative location .................................................................................. 16
4.4 Alternative design ................................................................................... 16
5. Plan conditions ..................................................................................... 17
6. Wind farm – environmental conditions and boundaries .......................... 18
6.1 National interests and area protection ......................................................... 18
6.2 Depth conditions and hydrology ................................................................. 28
6.3 Seabed conditions, sediments and pollution ................................................. 29
6.4 Bottom flora and fauna ............................................................................. 31
6.5 Fish ...................................................................................................... 32
6.6 Marine mammals ..................................................................................... 34
6.7 Birds ..................................................................................................... 36
6.8 Bats ...................................................................................................... 38
6.9 Cultural environment and marine archaeology .............................................. 39
6.10 Outdoor recreation .................................................................................. 41
6.11 Human health ......................................................................................... 41
6.12 Shipping and fairways .............................................................................. 42
6.13 Commercial fishing .................................................................................. 44
6.14 Military areas .......................................................................................... 45
6.15 Infrastructure ......................................................................................... 46
6.16 Monitoring stations .................................................................................. 48
ii
6.17 Raw material extraction sites ..................................................................... 48
7. Landscape view .................................................................................... 49
8. Marine Environment Directive and Water Framework Directive .............. 49
8.1 Marine Environment Directive .................................................................... 49
9. Risk analysis ........................................................................................ 51
10. Cumulative effects ................................................................................ 52
11. Surveys and investigations ................................................................... 52
11.1 Completed ............................................................................................. 52
11.2 Planned ................................................................................................. 53
12. Ongoing process ................................................................................... 54
12.1 Schedule for the planned activities ............................................................. 54
12.2 Timetable for the permit process ................................................................ 54
12.3 Continued consultation process and reviews ................................................. 54
12.4 Adjustments during the EIA process ........................................................... 54
13. Content of the environmental impact assessment and parties to be consulted ............................................................................................. 55
13.1 Delimitation of the environmental impact assessment .................................... 55
13.2 Parties consulted ..................................................................................... 57
14. References ........................................................................................... 58
1 of 61
1. Introduction
This document constitutes RWE Renewables Sweden AB’s basis for the delimitation
consultation ahead of the forthcoming application for a permit under the Swedish
Economic Zone Act (1992:1140) and the Continental Shelf Act (1966:314) for the
Södra Victoria offshore wind farm in the south-eastern Baltic Sea, and the
associated internal cable network.
The consultation document describes the proposed scope and format of the
environmental impact assessment (EIA) that will be attached to the company’s
future applications for permits under the Swedish Economic Zone Act for the
planned wind farm, as well as permits under the Continental Shelf Act for the
internal cable network within the wind farm.
1.1 Administrative details
Applicant RWE Renewables Sweden AB
Contact Anton Andersson
Company registration number 556938-6864
Address Box 388, SE-201 23 Malmö
Counsel for the applicant Foyen Advokatfirma KB, Pia Pehrson
1.2 Background RWE Renewables Sweden AB, formerly E.ON Wind Sweden AB (“RWE” or “the
company”) started exploring the possibilities for the establishment of a major
offshore wind farm in southern Sweden in 2006.
The company initially identified Södra Midsjöbanken, Norra Midsjöbanken and
Hoburgs Bank in the Baltic Sea as potential areas for offshore wind power. After
investigations, the company concluded that the possibilities for coexistence
between environmental assets and wind power were greatest at Södra
Midsjöbanken.
In 2007, the company applied for and received permission to investigate seabed
conditions at Södra Midsjöbanken and within a cable corridor to the shore under
the Continental Shelf Act (1966:314).
Following surveys, in 2012 the company applied for a permit under the Swedish
Economic Zone Act (1992:1140) to construct and operate a wind farm at Södra
Midsjöbanken, and under the Continental Shelf Act (1966:314) to lay and
maintain submarine cables for heavy current. The permit application also covered
additional seabed surveys.
In 2016, during the ongoing processing of the company’s permit applications, the
authorities designated a maritime area of more than 10,500 km2 in the Baltic Sea
as a Special Protection Area (SPA) under the Birds Directive. In 2017, the same
2 of 61
area was designated as a Site of Community Importance under the Habitats
Directive (SCI). The Natura 2000 area was named Hoburgs bank och
Midsjöbankarna (SE 0330308). The company’s proposed area of operation for the
wind farm was located entirely outside the designated Natura 2000 area.
The Government, through the Ministry of the Environment, announced in a letter
dated 14 March 2019 that RWE’s application for a permit under the Swedish
Economic Zone Act (1992:1140) had to be supplemented with a permit under
Chapter 7, Section 28a of the Environmental Code (i.e. a Natura 2000 permit).
In consultation responses concerning the company’s application for a permit under
the Swedish Economic Zone Act (1992:1140) and the Continental Shelf Act
(1966:314), objections were raised by authorities and experts against locating the
facility at the Södra Midsjöbanken offshore reef.
The company has subsequently carried out further studies of the conditions in the
area with a view to enabling an optimal location for the Södra Victoria wind farm.
Taking into account the conservation assets of the Natura 2000 area, including
birds, the Södra Victoria wind farm has been located to the west of the Södra
Midsjöbanken offshore bank instead of in the shallows, as in the application for a
permit in 2012.
On 10 June 2022, RWE submitted an application under Chapter 7, Section 28 of
the Environmental Code for the Södra Victoria wind farm and associated internal
cable network to the County Administrative Board of Kalmar, and is initiating
further permit processes with this consultation document.
1.3 Consultation document and consultation process The planned activities are expected to have a significant impact on the
environment. This means that a delimitation consultation must be carried out for
the specific environmental assessment process in accordance with Chapter 6,
Sections 29 to 34 of the Environmental Code.
The project area is located in the south-eastern Baltic Sea and transboundary
impacts cannot be excluded. The company is of the opinion that a notification
under the Convention on Environmental Impact Assessment in a Transboundary
Context (the Espoo Convention) is relevant. An Espoo consultation is administered
by the Swedish Environmental Protection Agency in a separate exercise.
The application for a Natura 2000 permit has been preceded by consultations and
an Espoo consultation. Some of the comments received from the Espoo
consultation were referred by the company to the upcoming review processes
under the Swedish Economic Zone Act and Continental Shelf Act. These comments
will be included in the forthcoming environmental impact assessment.
This document constitutes a basis for the delimitation consultation and contains
information on the location, scope and design of the planned wind farm, identified
interests and assets in the area, projected environmental impact and proposals for
3 of 61
the content and format of the EIA. The consultation concerns the examination of
permits under the Swedish Economic Zone Act for the construction of the wind
farm in the Swedish Economic Zone and the Continental Shelf Act for the laying of
internal submarine cables within the wind farm. The consultation document has
been prepared in accordance with Section 8 of the Environmental Assessment
Ordinance.
The consultation is advertised in local newspapers and in Post- och inrikes tidning.
A list of the proposed parties to be consulted can be found in section 13.2.
Consultation with Kalmar County Administrative Board, Gotland County
Administrative Board and the Geological Survey of Sweden, SGU, is planned to be
carried out through a meeting in August 2022. Consultation with other authorities,
municipalities and individuals particularly concerned is planned to take place in
writing in July and August 2022.
Comments on the formulation of the EIA and information on other matters should
be sent to [email protected] or to RWE Renewables Sweden AB, Box 388,
SE-201 23 Malmö.
The comments, facts and questions received during the consultation are an
important basis for RWE’s work on the project and, together with the results of in-
depth studies and inventories, will form the basis for the further design of the
project. The forthcoming permit application and associated EIA will be designed
and delimited on the basis of what emerges from the consultation.
The consultation will be described in a consultation report attached to the permit
application. The consultation report describes how the consultation was carried
out, what comments were received and an overview of how the comments were
taken into account in the design of the project or what is addressed in the EIA.
2. Legislation and permit processes
2.1 Applicable provisions and delimitation The whole of the wind power area is located outside Sweden’s maritime territory
in the Swedish Economic Zone, and permits for the construction and operation of
facilities are therefore examined under the Swedish Economic Zone Act
(1992:1140). Permits are issued by the Government (Ministry of the
Environment).
The submarine cables connecting the wind turbines and transformer substations
within the wind farm require permits under the Continental Shelf Act (1966:314).
Permits under the Continental Shelf Act are issued by the Government (Ministry of
Enterprise). This consultation does not include seabed analyses by means of
geophysical or geotechnical surveys of the seabed, which require permits under
the Continental Shelf Act.
4 of 61
The laying and operation of export cables which transmit electricity from the wind
farm to land require a permit under the Continental Shelf Act, Chapter 11 of the
Environmental Code and the Electricity Act (concession). The location of the
export cables can only be determined at a later stage of the project. These
permits will therefore be examined in separate processes and are not covered by
the current consultation. However, a general description of alternative cable
routes and connection points is presented in this consultation document in order
to provide an overall picture of the project.
The wind farm is located partly within the Natura 2000 area Hoburgs bank och
Midsjöbankarna, which means that a special Natura 2000 assessment under
Chapter 7, Section 28a of the Environmental Code is required for the construction
and operation of the wind farm and the internal cable network. This assessment is
taking place in a separate process where consultation has been carried out and
the application with the associated EIA has been submitted, ref. no. 5317-2022.
The assessment is being carried out by Kalmar County Administrative Board.
2.2 Environmental Impact Assessment According to the Swedish Economic Zone Act (1992:1140) and the Continental
Shelf Act (1966:314), an EIA must be prepared in accordance with the provisions
of the Environmental Code for applications for permits under the legislation. A
specific environmental assessment must be carried out in order to obtain the right
knowledge about the project, to narrow down the investigation and impact
assessment to what is essential and to investigate various alternative locations
and designs for the planned activity. The specific environmental assessment also
aims to obtain information on the conditions for the planned activity, and the
effects of these. This information will be used as a basis for decision-making in the
planning and EIA process. Delimitation consultations are carried out as part of the
specific environmental assessment: see section 1.2.
This delimitation consultation sets out the changes to the environment that are
likely to occur and the assets that these changes may affect. By analysing the
assets and aspects that may be affected at an early stage, the relevant supporting
material in the form of inventories and studies can be performed at the right level.
Early analysis of the anticipated environmental impact also provides an overall
picture of the project’s potential impacts, and adjustments in respect of wind farm
design, cable routing and protection measures may be implemented.
An overall assessment of the impact of the wind farm and its internal cable
network is appropriate, even if the assessment is carried out under different
legislation (Swedish Economic Zone Act and Continental Shelf Act). Therefore, a
design will be sought such that permit applications under different parts of the
legislation can relate to specific parts of the EIA.
2.3 Review When the application with the EIA and technical description has been submitted to
the Government, a update and consultation procedure will be initiated, during
5 of 61
which it will also be possible to submit comments and observations on the planned
activities.
3. Activity description
3.1 Location The planned Södra Victoria wind farm is located in the south-eastern Baltic Sea,
about 70 km south-east of the southern tip of Öland, about 90 km north-west of
the northernmost coast of Poland and about 130 km east of Bornholm. The wind
farm is located outside Sweden’s territorial boundary and within the Swedish
Economic Zone. Figure 1 shows the location of the Södra Victoria wind farm.
Figure 1. Location of the planned Södra Victoria wind farm.
The area of the planned wind farm is 174 km2. The depth varies between about 25
and 36 m. In the eastern part of the wind farm, there are small areas at a depth
of about 23 m. Figure 2 shows the approximate depth and coordinates of the
outer boundary of the planned wind farm.
6 of 61
Figure 2. The approximate depth and coordinates of the outer boundary of the planned Södra Victoria wind farm.
3.2 Design The final choice of wind turbine and its design has not yet been determined due to
the rapid technological development in offshore wind power. However, Table 1
shows a worst case scenario (WCS) design for the parameters that are planned to
form the basis of the forthcoming EIA.
Table 1. Summary technical parameters for the Södra Victoria wind farm.
Parameters
Nameplate capacity 1500–2000 MW
Area 174 km2
Number of wind turbines, max. 100
Height of wind turbines (including
rotor blades), max.
295 m
Rotor diameter, max. 270 m
Rotor height above sea level 20 m
Shortest distance between wind
turbines:
Approx. 1000 m
Internal cable network Approx. 150 km
Transformer substations 1-2
The final location of individual turbines within the wind farm area will be
determined in connection with the detailed design of the wind farm and cannot be
specified at this stage. The location of individual wind turbines is influenced by
7 of 61
parameters such as wind conditions, water depth, geology, environmental assets,
optimisation of the route of the internal cable network and the size of the wind
turbines. Figure 3 shows an example layout involving 100 wind turbines, a
transformer substation and the internal cable network.
Figure 3. Example layout of the planned wind farm with 100 wind turbines, a centrally located transformer substation and internal cable network.
3.3 Technical description
3.3.1 Design and technology
3.3.1.1 Wind turbines A wind turbine consists of four main components; a foundation, a tower, a nacelle
and three rotor blades: see Figure 4. The tower is made of steel and is mounted
on a foundation anchored to the seabed. Foundations are described in section
3.3.1.3. The rotor blades are mounted on a hub located on the nacelle. The
nacelle, which is located at the top of the tower, houses the generator, among
other things. The generator supplies power to the transformer via the internal
cable network. After the transformer, the electrical energy is transferred to the
export cables.
8 of 61
Figure 4. Outline drawing of a wind turbine. (Source: RWE)
The wind turbines are planned to be a maximum of 295 m high, with a maximum
rotor diameter of 270 m and a minimum rotor height above sea level of 20 m at
high tide (“Highest Astronomical Tide” – HAT).
3.3.1.2 Transformer substation The transformer substations are the nodes between the wind turbines and the
main grid. At the transformer substations, the electricity generated in the wind
turbines is transformed to a higher voltage level, from about 66-130 kV AC to
about 220 kV AC or 500 kV DC, depending on the choice of technology. The
number of export cables can be reduced and energy losses reduced by converting
to a higher voltage level.
Transformer substations typically consist of two parts; a foundation and the
station itself. The station houses switchgear and transformers, as well as an
auxiliary power unit. The auxiliary power unit consists of diesel-powered
generators that supply 400 V power to the low-voltage installation on the platform
in the event of loss of the primary power supply. There are mooring spaces for
boats on the platform. The platform may be equipped with a helicopter pad and an
accommodation module for personnel.
The size of the platforms, depending on whether they handle AC or DC power, is
shown in Table 2. The final design and size of the transformer substations may
differ slightly from these typical examples in Table 2.
9 of 61
Table 2. Size of transformer substations (example) depending on whether they handle AC or DC power.
Transformer substation Length x width x height:
Direct current 80 x 35 x 35 m
Alternating current 45 x 30 x 15 m
The transformer substations are equipped with collection systems for any oil spills
and leaks.
3.3.1.3 Foundations Wind turbines and transformer substations are mounted on foundations that are
anchored to the seabed. The most suitable foundations depend on factors such as
foundation conditions, which may vary within the planned wind farm area. This will
be clarified during detailed design.
Possible options for the foundation of wind turbines are gravity foundations and
the piled foundation types: monopile foundations and truss foundations; see
Figure 5. Possible foundation options for the transformer substations are truss
foundations and gravity foundations. Monopile foundations are not considered a
relevant option for transformer substations.
Figure 5. Types of foundations that may be used for the planned wind farm. From left to right; monopile foundations, truss foundations and gravity foundations. (Source: RWE)
Monopile foundations
The monopile foundation is a steel structure that is anchored to the seabed by
means of piling. Steel monopile foundation is a tried and tested technology that is
traditionally preferred for offshore wind farms as it is well established in the
market and is economically advantageous. The monopile foundation consists of
two parts; a steel cylinder that is driven into the seabed, and a transition piece
that is mounted on top of the cylinder. The tower is attached to the foundation by
means of the transition piece. Monopile foundations are generally considered to be
suitable for water depths up to about 40 m.
10 of 61
Truss foundations
A truss foundation for a wind turbine consists of a prefabricated network structure
made up of steel tubing with three to four legs anchored by three or four piles that
are driven into the seabed. Truss foundations with four legs, as opposed to three
legs, are the most likely to be used within the planned wind farm. In stormy
conditions, the force on each individual pile can be very high. Ballast can be
installed in the piles to counteract this force. Truss structures are commonly used
in the oil and gas industry. The foundations are generally considered suitable for
water depths up to 60 m.
Truss foundations for a transformer substation typically consist of a steel structure
with up to eight supporting legs, with a diameter of about 2.5-3.5 m per leg.
Cable ducts for electricity and fibre cables run between the seabed and the
switchgear and are designed to protect the cables from external influences.
Gravity foundations
Gravity foundations consist of very large concrete structures that hold wind
turbines and transformer substations in place with their large size and weight.
Gravity foundations are used, for example, at RWE’s existing Kårehamn wind farm
off Öland, and are generally considered suitable for water depths up to about 40
m.
The construction of gravity foundations does not require deep countersinking in
the seabed and, after possible preparatory preparation of the seabed, may be
suitable for rocky beds and boulder-rich terrain, as well as for stable (well-packed)
sediments. Gravity foundations, on the other hand, are less suitable on beds
consisting of continuous loose sediment such as clay.
There are two possible concepts if the transformer substations are established on
gravity foundations: see Figure 6. Either gravity foundations are supplied to the
site complete with ballast installed in the bottom part, Or gravity foundations are
supplied without ballast, but in the form of a bottom part with a “balcony”, see
Figure 6. The balcony is filled with ballast when the foundation is in place.
11 of 61
Figure 6. There are two possible concepts for the gravity foundation; supplied complete with ballast placed in the bottom part (top picture) or supplied without ballast in the form of a bottom part with a “balcony” (bottom picture). The foundation is put in place and then the “balcony” is filled with ballast. (Source: RWE)
3.3.1.4 Erosion protection Depending on the nature of the seabed, there is a risk of erosion around installed
foundations due to sea currents. Erosion can result in undermining of foundations,
which causes them to lose their anchorage to the substrate material, which in a
worst case scenario can lead to failure. Erosion of the seabed can be prevented by
installing erosion protection around the foundations.
Erosion protection usually consists of a gravel or stone layer and boulders placed
around the foundation. Alternative erosion protection measures include gabions or
nets filled with material excavated from the seabed during construction works,
which are placed around the foundations.
Gravity foundations almost always require erosion protection. Monopile and truss
foundations may also require erosion protection, but to a lesser extent than
gravity foundations. Truss foundations require greater amounts of erosion
protection than monopile foundations due to the many legs in the truss structure.
12 of 61
The need for and extent of erosion protection for foundations in the planned Södra
Victoria wind farm depends not only on the foundation technology, but also on the
susceptibility of the seabed to erosion, which can vary within the wind farm area.
The detailed design of the wind farm will determine whether erosion protection is
needed around all or just some of the foundations and how extensive the erosion
protection needs to be. As a starting point for the environmental assessment, it is
assumed that erosion protection will be installed around all foundations.
Wind turbines
Erosion protection with a maximum outer radius equivalent to five times the
diameter of the foundation may need to be installed for monopile foundations and
truss foundations for wind turbines. Erosion protection is placed about 15 m from
the gravity foundations in the case of gravity foundations for wind turbines. If the
surface for the gravity foundation needs to be dredged in order to level the
seabed, it will be placed 10-20 m outside the edge of the erosion protection.
Transformer substation
Depending on the nature of the seabed, erosion protection for the truss
foundations belonging to the transformer substations may require construction of
erosion protection in the form of a rock bed on which the foundations and power
cables can rest. The thickness of the bed is estimated to be 1-2 m and extends at
most about 15 m beyond the foundation. Depending on the nature of the seabed,
it may also be necessary to construct erosion protection for the gravity
foundations belonging to the transformer substations. The bed may extend a
maximum of about 15 m beyond the foundation. If dredging is required, the
dredged material will be placed around the foundation, outside the erosion
protection. Dredged material may extend about 20 metres beyond the erosion
protection.
3.3.1.5 Internal cable network The internal cable network will probably consist of high-voltage AC cables for
approx. 66 – 130kV. Higher voltage levels could also be used. The total length of
the cable network is estimated to be about 150 km. This length depends on
factors such as the final number of wind turbines and transformer substations, the
voltage level of the cable and the layout of the wind farm.
3.3.1.6 Export cables The export cables are not included in this consultation, but are presented in
summary to provide a better overall picture of the project.
Power will be transferred from the transformer substations at the planned wind
farm to the main grid via export cables. Three different connection options are
being examined for the Södra Victoria wind farm:
• The export cables will be laid between the transformer substations and a
connection point on the Swedish mainland.
• The export cables will be laid between the transformer substations and a
future offshore connection point.
13 of 61
• The export cables from the transformer substations will be connected to
the existing NordBalt power cable, which is adjacent to the planned wind
farm.
Regardless of the connection option, the cables will be laid within the cable
corridor shown in Figure 7. The exact routing of the cables within the corridor as
well as their landfall will be examined in detail at a later design stage. When
connecting to the NordBalt cable, the existing cables will be respliced in a suitable
location and installed within the export cable corridor to the transformer for the
planned wind farm.
Figure 7. The planned wind farm including the cable corridor for the export cable
to land.
The power transmission from the wind farm is either by high-voltage alternating
current (HVAC) cables or high-voltage direct current (HVDC) cables. The number
and design of the cables will depend on the selected technology (HVAC or HVDC)
and the voltage level of the cables. A decision on the choice of technology will be
made at a later stage following coordination with Svenska Kraftnät, so both
technologies are possible alternatives.
14 of 61
3.3.2 Planned work
3.3.2.1 Construction The construction of the planned wind farm is planned to take about 2-4 years.
Foundation
The project includes the construction and installation of foundations, wind
turbines, transformer substation and internal cable network.
Monopile and truss foundations do not usually require any ground preparation or
other preparatory work apart from the clearing of any boulders and suchlike. The
foundations are towed to the site and set out using a crane from a construction
vessel. The installation work can be roughly divided into the following activities:
• Docking of vessels and placement of foundations in an upright position for
piling
• Installation of soundproofing measures
• Piling work by means of pile driving, supplemented by drilling if necessary
(giving rise to drill cuttings)
• Removal of soundproofing measures
• Transfer to a new position
After piling, the transition piece is mounted on the monopile or truss foundation,
after which any erosion protection is constructed.
Gravity foundations are constructed in several steps. If necessary, the seabed at
the foundation site will be prepared by means of dredging to remove any loose
sediment and level the surface of the seabed. Excavated sediments will be
deposited on the seabed adjacent to the dredged area or used to cover the
internal cable network. A bed with a base course made up of crushed rock is
usually laid on the dredged surface. The gravity foundations, in the form of
concrete caissons, can be transported to the wind farm area by barge.
Alternatively, the foundations may be designed as floating/semi-floating and
towed to the wind farm area. Erosion protection is built around the foundations
after the gravity foundations have been installed.
Internal cable network
The internal cable network is constructed when the foundations have been
installed. Installation is carried out using a cable-laying vessel from which the
cable is laid on the seabed. The cable is then anchored and stabilised on the
seabed using rocks, concrete mattresses or similar at regular intervals. The
installation may need to be preceded by potential clearing of boulders and suchlike
on the seabed within the corridor where the internal cable is to be placed. The
internal cable network is planned to avoid laying it on reefs. If this is not possible
on shorter sections, the reef will be raised to one side and repositioned with the
same orientation after the cable is laid down.
Wind turbines and transformer substation
There are several alternative procedures for the installation of wind turbines:
15 of 61
• The rotor is assembled on land and transported to the construction site
and mounted on the erected tower and nacelle
• The blades are mounted, one by one, on the erected nacelle on site
The parts are transported by ship to the planned wind farm. Towers and nacelles
can be installed on the foundations by various barge solutions, or by vessels using
support legs to allow safe lifting. The installation work is mainly carried out above
the surface of the water.
The transformer substations are constructed in a similar way to the wind turbines.
The transformer substation is lifted into place after a foundation is installed.
Export cable
A number of different methods may be used to lay the export cables from the
transformer substations to a connection point on land or at sea. The choice of
method (subsea ploughing/excavation and milling) will depend on local seabed
conditions, and different methods may be used for different parts of the cable
network if seabed conditions so require. The company believes that any milling
will only need to be carried out in exceptional cases on certain sections, if
conditions so require.
The export cables are installed at a depth of about 1-2 m into the seabed to
protect them from external influences and from damage caused by fishing gear
and anchors, for example. The minimum depth is one metre. If this cannot be
achieved, or if there are locations where excavation may be difficult, the cable
may be placed on the seabed and anchored using crushed rock.
3.3.2.2 Operation Regular inspection and maintenance of the various parts of the planned wind farm
will take place during the operational phase.
The transformer substations are unlikely to be staffed 24 hours a day, but will be
visited regularly by staff for inspection and maintenance. Transportation of
personnel to and from the wind farm area be by ship, and possibly by helicopter.
Personnel responsible for inspection and maintenance may stay in an
accommodation area on the transformer platform or on vessels. Site conditions
such as wind are monitored by means of survey buoys.
The large number of wind turbines and other equipment means that there will be
constant inspection of the wind farm throughout its lifetime, which is estimated to
be at least around 35 years.
3.3.2.3 Decommissioning The decommissioning phase is further into the future and methods may be
different when decommissioning is to be implemented. The decommissioning
phase and its effects will be described based on current practices, techniques and
methodologies, but these may be subject to change when decommissioning is
imminent.
16 of 61
Decommissioning and its possible consequences will be outlined in the EIA
4. Options
An EIA must include a statement of options. Alternatives to a wind farm as large
as the planned Södra Victoria wind farm are hard to find on land, which is why
only offshore options are being investigated. Furthermore, RWE intends to connect
the electricity produced to electricity area 4, which means that only sites at a
reasonable distance from connection points in these areas are considered.
4.1 Main option The main option involves locating and designing the wind farm in general
conformity with the description in chapter 3. The fully developed wind farm will
have a total nameplate capacity of about 1500-2000 MW. The construction work is
expected to take about 2-4 years.
Impacts, effects and consequences will be assessed during construction and
operation and for decommissioning. A preliminary assessment has been carried
out for each aspect under chapter 6.
4.2 The zero option The zero option means that no wind farm will be built in the area and thus no
renewable energy will be produced from this area. As a result, the national
interest in wind energy is not taken into account and electricity generation needs
to be relocated.
The zero option is generally taken to mean that there will be no impact on natural
assets and other interests in the area. However, similar impacts may occur in
another location where energy production is constructed. The zero option will be
described in the EIA.
4.3 Alternative location RWE has commissioned a localisation survey, identifying and comparing
alternative locations for an offshore wind farm in the southern Baltic Sea (Sweco,
2022c). The alternatives have been evaluated in terms of technical conditions,
impact on protected areas and natural assets, and impact on other interests.
Parameters taken into account include the size of the project area, sea depth,
wind speed, electricity connection and coexistence with nature conservation and
other interests, such as shipping, defence and the fishing industry. Alternative
locations will be described in the EIA.
4.4 Alternative design Alternative designs could, for example, include different ways of laying the
foundations for the turbines or different cable installation methods. Foundations
could be monopile foundations, truss foundations or gravity foundations, for
example.
17 of 61
An alternative design for the wind farm will be presented in the EIA.
5. Plan conditions
The Swedish Government established Sweden’s marine plans for the Gulf of
Bothnia, the Baltic Sea and the North Sea in February 2022 (Havs- och
vattenmyndigheten, 2022b). The purpose of the marine plans is to define clear
goals for the future that Sweden wishes to achieve with regard to the sea and
contribute to sustainable development. The plans show the Government’s overall
view of how the sea should be used, and are intended to guide authorities,
municipalities and courts when they make decisions, plan or grant permits for
activities at sea.
The area of the Södra Victoria wind farm coincides with areas Ö248 and Ö245 in
the marine plan: see Figure 8. Area Ö248 (Södra Midsjöbanken) is a survey area
for energy extraction where special consideration must be given to the interests of
total defence and the area’s high conservation values. Area Ö245, the Natura
2000 area Hoburgs bank och Midsjöbankarna, has “nature” use. The planned
Södra Victoria wind farm, which is located in its entirety within an area of national
interest for wind energy – see Figure 8 – is mainly located outside and west of
area Ö248.
18 of 61
Figure 8. Plan map showing south-eastern and southern Baltic Sea areas (Havs-
och vattenmyndigheten, 2022d).
The part of Södra Midsjöbanken located within the Polish Economic Zone, and the
immediate surrounding sea area, are areas for exploration and extraction of
minerals and production of renewable energy according to the Polish maritime
plan. Fairways designated for transport pass to the south and south-west of Södra
Midsjöbanken.
6. Wind farm – environmental conditions and boundaries
6.1 National interests and area protection
6.1.1 National interest: wind energy The Swedish Energy Agency has been tasked with identifying areas on land and at
sea with particularly good wind conditions that are of national interest for wind
19 of 61
energy in accordance with Chapter 3, Section 8 of the Environmental Code. The
national interest claims specified have been devised with security of supply and an
energy system perspective in mind (Energimyndigheten, 2022).
6.1.1.1 Baseline description The planned wind farm in its entirety is located within an area of national interest
for wind energy in accordance with Chapter 3, Section 8 of the Environmental
Code Figure 9.
Figure 9. National interest for wind energy (Energimyndigheten, 2022).
6.1.1.2 Possible impacts Establishment of a wind farm within the designated national interest means that
the purpose of the national interest is fulfilled.
6.1.1.3 Delimitation Impacts on designated national interests for wind energy will be investigated and
assessed further in the forthcoming EIA.
20 of 61
6.1.2 National interest: nature conservation and nature reserves Areas of national interest for nature conservation represent the main features of
Swedish nature and are the most valuable areas from a national perspective. The
Swedish Environmental Protection Agency is responsible for identifying areas that
are deemed to be of national interest for nature conservation in accordance with
Chapter 3, Section 6 of the Environmental Code (Naturvårdsverket, 2005).
County administrative boards and municipalities can establish nature reserves.
Nature reserves are created in order to preserve biodiversity, maintain and
conserve valuable natural environments and provide areas for outdoor recreation.
An area that is needed in order to protect, restore or recreate valuable natural
habitats or biotopes for species worthy of protection may also be declared a
nature reserve (Naturvårdsverket, 2022).
6.1.2.1 Baseline description The nearest designated national interest is located about 65 km north-west of the
wind farm and includes the southern cape of Öland.
6.1.2.2 Possible impacts No impacts on the designated national interest for nature conservation are
expected because of the large distance from the planned wind farm.
6.1.2.3 Delimitation Designated national interests for nature conservation will be reported in the
forthcoming EIA, but no assessment is proposed as no impacts are foreseen.
6.1.3 National interest: cultural environment The Swedish National Heritage Board is responsible for the national coordination of
national interests for cultural conservation in accordance with Chapter 3, Section 6
of the Environmental Code. Farming environments, town centres, older farming
landscapes and post-war buildings are examples of national interests for cultural
conservation. The national interest areas should collectively reflect the history of
the whole country by means of clear examples of different historical activities and
processes (Riksantikvarieämbetet, 2021).
6.1.3.1 Baseline description The nearest designated national interest is located approximately 65 km north-
west of the wind farm and includes the southern cape of Öland.
6.1.3.2 Possible impacts No impacts on the designated national interest for cultural conservation are
expected because of the large distance from the planned wind farm.
6.1.3.3 Delimitation Designated national interests for cultural conservation will be reported in the
forthcoming EIA, but no assessment is proposed as no impacts are foreseen.
6.1.4 National interest: outdoor recreation For an area to be of national interest for outdoor recreation, it must have high
outdoor recreational values from a national perspective based on specific natural
21 of 61
and cultural qualities, variations in the landscape and ease of access for the
general public. The Swedish Environmental Protection Agency is responsible for
identifying areas that are deemed to be of national interest for outdoor recreation
in accordance with Chapter 3, Section 6 of the Environmental Code
(Naturvårdsverket, 2005).
6.1.4.1 Baseline description The nearest designated national interest is located approximately 65 km north-
west of the wind farm and includes the southern cape of Öland.
6.1.4.2 Possible impacts No impacts on the designated national interest for outdoor recreation are expected
because of the large distance from the planned wind farm.
6.1.4.3 Delimitation Designated national interests for outdoor recreation will be reported in the
forthcoming EIA, but no assessment is proposed as no impacts are foreseen.
6.1.5 National interest: total defence National interests for the military component of total defence include national
interests that can be disclosed openly and national interests that cannot be
disclosed openly for reasons of defence secrecy. The national interests of the
Swedish Armed Forces include firing and training ranges, airports, naval training
areas, technical systems and facilities. Areas that constitute national interests in
accordance with Chapter 3, Section 9 of the Environmental Code for the military
component of total defence are areas that are deemed to have nationally
important values and qualities for the protection of Sweden (Försvarsmakten,
2020).
6.1.5.1 Baseline description The wind farm is not adjacent to any known Swedish defence area. The TM0306
naval training area is situated closer to land, about 63 km north-west of the wind
farm.
6.1.5.2 Possible impacts No possible impacts can be foreseen for designated national interests for total
defence that are not disclosed openly. RWE intends to consult and maintain
dialogue with the Swedish Armed Forces.
6.1.5.3 Delimitation Delimitation for national interests for total defence will need to take place in
consultation with the Swedish Armed Forces so the necessary investigations can
be carried out. If effects are deemed to be capable of occurring on designated
national interests for total defence, these will be reported in the forthcoming EIA.
No possible impacts are expected for designated national interests for total
defence that are disclosed openly.
6.1.6 National interest: commercial fishing Areas of national interest for commercial fishing are designated in the marine
area, lakes and watercourses, and for fishing ports. The Swedish Agency for
22 of 61
Marine and Water Management provides information on areas of national interest
for commercial fishing in accordance with Chapter 3, Section 5 of the
Environmental Code.
6.1.6.1 Baseline description About 12 km west of the wind farm, there is a fishing area of national interest for
commercial fishing known as “Södra Öland/Utklippan”, with the designation RI YF
8 (Havs- och vattenmyndigheten, 2020): see Figure 10.
Figure 10. National interest: commercial fishing (Havs- och vattenmyndigheten, 2020).
6.1.6.2 Possible impacts Possible impacts on the fishing area during construction, operation and
decommissioning are described in section 6.13, and these are the effects that are
also considered likely to occur for the designated national interest for commercial
fishing.
23 of 61
6.1.6.3 Delimitation The impact of construction, operation and decommissioning on the national
interest for commercial fishing will be further investigated and assessed in the
forthcoming EIA.
6.1.7 National interest: shipping and fairways The Swedish Transport Administration is responsible for making national interest
claims for modes of transport, including ports and fairways, in accordance with
Chapter 3, Section 8 of the Environmental Code.
6.1.7.1 Baseline description There are two deep-water fairways north of the wind farm, “Gedser-Stora Björn”
and “Ölands södra udde-Finska viken”, where a total of about 40,000 vessels pass
each year. This includes cargo vessels, tankers and passenger vessels. The
“Utklippan-Gdansk (Poland)” fairway runs south-west of the wind farm.
Figure 11. National interest: shipping and fairways (Trafikverket, 2021).
24 of 61
6.1.7.2 Possible impacts The wind farm, which is entirely outside the fairways described above, does not
affect the national interest for communications (shipping). Different types of
vessels related to the project will operate in the area of the planned wind farm
during the construction and decommissioning phases, and this could affect nearby
shipping.
6.1.7.3 Delimitation The impact of the construction, operational and decommissioning phases on
shipping and fairways will be further investigated and assessed in the forthcoming
EIA.
6.1.8 Natura 2000 The Natura 2000 network of protected areas in the EU was set up in order to halt
the extinction of animals and plants and prevent the destruction of their habitats.
Natura 2000 areas are designated pursuant to two EU Directives: the Birds
Directive and the Habitats Directive. Areas that are designated to comply with the
Birds Directive are known as SPAs (Special Protected Areas), while areas
designated under the criteria in the Habitats Directive are known as SCIs (Sites of
Community Importance).
6.1.8.1 Baseline description Figure 12 shows Natura 2000 areas in and around the planned wind farm.
25 of 61
Figure 12. Natura 2000 areas in and around the planned wind farm. The Natura 2000 area Hoburgs bank och Midsjöbankarna, which overlaps with the planned wind farm, is being examined in a separate exercise under Chapter 7, Section 28a of the Environmental Code, and an application has been compiled and submitted (EEA, 2022).
The planned wind farm is partly located within the Natura 2000 area Hoburgs bank
och Midsjöbankarna (SE0330308), which is an SPA and an SCI. Designated
habitats are sandbanks (1110) and reefs (1170) and designated species are long-
tailed duck (A064), black guillemot (A202), harbour porpoise (1351) and eider
(A063). These banks are important feeding and nursery areas for fish and sea
birds, and together they form the most important wintering area in the Baltic Sea
for long-tailed ducks and a core area for the Baltic harbour porpoise population
(Länsstyrelsen Gotland län och Kalmar län, 2021).
The Natura 2000 area Hoburgs bank och Midsjöbankarna is being examined in a
separate exercise under Chapter 7, Section 28a of the Environmental Code for
what is known as a Natura 2000 permit for the wind farm and its associated
internal cable network. This application, together with an accompanying EIA and
26 of 61
annexes, has been prepared and submitted for examination. In view of this,
potential impacts on the Natura 2000 area Hoburgs bank och Midsjöbankarna will
not be addressed further in this consultation document beyond this baseline
description.
The Natura 2000 area Ławica Słupska (PLC990001), which is both an SPA and an
SCI, is situated in Polish waters about 60 km south of the planned wind farm.
Sandbanks (1110) and reefs (1170) are designated habitats, while black guillemot
(A202), long-tailed duck (A064), black-throated diver and red-throated diver
(A002 and A001 respectively) are designated species.
The Natura 2000 area Ottenby NR (SE0330108), which is an SCI, is situated on
the southern tip of Öland, about 65 km north of the planned wind farm
(Länsstyrelsen Kalmar län, 2016). Designated marine habitats are sandbanks
(1110), mudflats and sandflats not covered by seawater at low tide (1140),
coastal lagoons (1150), large shallow inlets and bays (1160) and reefs (1170).
Designated species include the grey seal (1364) and the common seal (1365). The
Natura 2000 area Ottenby NR includes the Natura 2000 area Ottenby
(SE0330083), which is an SPA with several designated bird species (Länsstyrelsen
Kalmar län, 2016). The common Natura 2000 area has – among other things – a
unique environment, with riparian cultivated land and important marine habitats
to which many species-rich plant and animal communities are linked.
6.1.8.2 Possible impacts Underwater noise will be generated during construction, operation and
decommissioning which may affect both fish and marine mammals: see also
sections 6.5 and 6.6 respectively. Installation and decommissioning may produce
loud noise levels that could cause flight behaviour and affect their hearing and, in
a worst case scenario, could be fatal. The provision of a wind farm in the project
area will change the underwater soundscape while the wind farm is in operation.
Underwater noise will not affect these areas during any phase of the planned wind
farm due to the long distance to Natura 2000 areas.
Temporary changes in water quality may occur during construction and
decommissioning due to turbidity, sedimentation and possible release of
pollutants. The turbidity and hence sedimentation and possible release of
pollutants will not affect the Natura 2000 areas as these areas are located a very
long distance from the planned wind farm.
Birds may be affected during construction and operation due to the physical
presence of project-related vessels within the planned wind farm and en route to
the planned wind farm. Vessels will be present and construction works will be
carried out during construction, which may affect birds. Collisions with the wind
turbines or barrier effects for birds may occur during operation due to the planned
wind farm, as well as possible exclusion of birds from areas in which they forage.
See also section 6.7 on birds.
27 of 61
6.1.8.3 Delimitation Natura 2000 areas will be detailed in the forthcoming EIA. There will be no impact
on designated habitats or species or their conservation status because of the great
distance to the Natura 2000 areas other than Hoburgs bank och Midsjöbankarna,
which is being assessed in a separate exercise. Therefore, their impact will not be
assessed in the EIA. Therefore, assessment under the Natura 2000 provisions for
these Natura 2000 areas, which are not Hoburgs bank och Midsjöbankarna, is not
considered to be relevant.
6.1.9 International protection HELCOM (the Helsinki Commission) is the governing body of the “Convention on
the Protection of the Marine Environment of the Baltic sea area”. The HELCOM
Marine Protected Area (MPA) network aims to protect marine and coastal habitats
and species specific to the Baltic Sea (HELCOM, 2021).
6.1.9.1 Baseline description There is a Marine Protected Area (MPA) located at Norra Midsjöbanken, just over
30 km north of the wind farm. A Marine Protected Area, the Torhamn archipelago,
is located about 80 km north-west of the wind farm. Another protected area,
Ławica Słupska off the coast of Poland, is located about 60 km south of the wind
farm, Figure 13.
28 of 61
Figure 13. Marine Protected Areas (MPAs) within HELCOM around the planned wind farm (HELCOM, 2022).
6.1.9.2 Possible impacts No impacts are expected for the Marine Protected Areas (MPAs), as these areas
are not in the vicinity of the planned wind farm.
6.1.9.3 Delimitation MPAs will be reported in the forthcoming EIA but will not be assessed as no
impacts are foreseen.
6.2 Depth conditions and hydrology Depths within the area of the planned wind farm increase mainly from east to
west, and range from about 23 to 36 metres: see Figure 2. The Södra
Midsjöbanken shallows are located east of the planned wind farm.
The Baltic Sea is an almost closed brackish inland sea. Salinity is relatively low
because the Baltic Sea has few inflows of saltier water across the Great and Little
Belts and Öresund, compared to relatively high inflows of freshwater from land
and precipitation.
29 of 61
The limited inflows of salt-rich and oxygen-rich water from the North Sea into the
Baltic Sea, together with the high freshwater inflows from land and precipitation,
cause sharp stratification of water that can prevent oxygenation of deeper waters
and give rise to oxygen-depleted or completely oxygen-free seabeds (SMHI,
2018). Figure 14 shows areas with oxygen-depleted or completely oxygen-free
seabeds in autumn 2020. If the oxygen content is sufficiently low, hydrogen
sulphide will be produced as organic matter decomposes. Hydrogen sulphide is
toxic and the animals that are unable to leave these areas will die, which will
further increase the concentration of hydrogen sulphide. Anoxic and oxygen-free
seabeds have low biodiversity because of this. Inflows through the Great and Little
Belts and Öresund that are great enough to improve oxygen conditions on the
deep seabeds are very rare: the last two such inflows occurred in 2014 and 2003
(SMHI, 2020; SMHI, 2022; SMHI, 2012).
Figure 14 Oxygen-deficient or oxygen-free seabed areas in the vicinity of the planned Södra Victoria wind farm (SMHI, 2022).
6.3 Seabed conditions, sediments and pollution According to the sediment sampling carried out, the area of the planned wind
farm’s seabed material is classified as a sandbank, as the top layer of the seabed
30 of 61
is dominated by sand with elements of gravel, as well as the presence of rocks
and boulders (Ocean Ecology, 2022; SGU, 2022). Figure 15 shows the dominant
seabed material in the top metre of the seabed.
Figure 15. Illustration of the seabed material dominating the top metre of the project area (SGU, 2022).
Sampling also indicates that the surface sediments within the project area
generally contain very low to low concentrations of substances (class 1 and 2,
respectively). Measured concentrations of metals (cadmium, copper and lead) and
PAHs (anthracene and fluoranthene) are below the assessment limit for applicable
environmental quality standards (Marine Monitoring AB, 2022).
According to the Swedish Agency for Marine and Water Management, there is
dumped ammunition and a risk of submerged mines in Hoburgs bank och
Midsjöbankarna (area Ö245) and Södra Midsjöbanken (Ö248) (Havs- och
vattenmyndigheten, 2022d).
31 of 61
6.4 Bottom flora and fauna
6.4.1 Baseline description Bottom vegetation and fauna, also known as benthic flora and fauna, includes
plants and animal organisms that live on or in the seabed.
Bottom vegetation
Bottom vegetation consists of macroalgae and various types of seaweed. Bottom
vegetation in the Baltic Sea is mainly limited by the availability of light, which is
related to the depth and turbidity of the water. Usually there is very little light
available at depths greater than 20 m. However, macroalgae were found down to
a depth of more than 30 m during surveys of Södra Midsjöbanken
(Naturvårdsverket, 2006). Bottom vegetation is considered to be limited as the
depths within the area of the planned wind farm vary from about 23 to 36 metres
(see section 6.2), but there may still be areas of vegetation, particularly on the
eastern side where the depths are slightly shallower. Seabed surveys carried out
in 2021 confirm this and the presence of red algae in the project area (Ocean
Ecology, 2022).
Bottom fauna
The species composition of benthic fauna populations in the Baltic Sea is
dependent on various biotic and abiotic factors. The physical conditions that
govern the composition of bottom fauna are mainly substrate type (including any
reef structures), light, salinity, temperature, oxygen content, organic matter and
water movement, but also water quality. As the Baltic Sea has brackish waters
and many limnic and marine species are not adapted to such conditions, benthic
biodiversity is limited compared to the west coast of Sweden, where oceanic
conditions prevail. The bottom fauna in the area is therefore mainly made up of
opportunist species with high growth rates and short life cycles, such as several
species of polychaetes and bivalves (Bivalvia). Studies and surveys confirmed that
the species composition was dominated by mussels, Baltic macoma and annelids,
but also the presence of cnidarians, molluscs, arthropods and amphipods
(Naturvårdsverket, 2006; Ocean Ecology, 2022).
6.4.2 Possible impacts Bottom vegetation and fauna may be affected during construction of the planned
wind farm as the structures will occupy the seabed, and during decommissioning if
the structures are removed. Bottom vegetation and fauna may also be affected
during construction and decommissioning due to the methods used to install and
remove structures within the project area. These practices may cause increased
levels of suspended sediment, release of pollutants and sedimentation, which may
affect bottom species by way of impaired photosynthesis or smothering of sessile
animals, for example. During the operational phase, the structures at the planned
wind farm will produce what is known as a reef effect, as the foundations of the
wind turbines create new structures where hardground species can grow.
6.4.3 Delimitation As bottom vegetation may occur within the project area and may potentially be
affected by the planned wind farm, impacts of the construction, operational and
32 of 61
decommissioning phases on bottom vegetation will be further investigated and
assessed in the forthcoming EIA.
For the same reason, the impact of the construction, operational and
decommissioning phases on bottom fauna will be further investigated and
assessed in the forthcoming EIA.
6.5 Fish
6.5.1 Baseline description The most abundant fish species at Hoburgs bank och Midsjöbankarna and Södra
Midsjöbanken are cod, herring, lumpfish, flounder, sprat, three-spined stickleback,
fourbeard rockling, shorthorn sculpin, plaice and turbot. Eel, salmon and sea trout
are migratory fish species that may temporarily be found in the area (Marine
Monitoring AB, 2022).
In 2010, the Swedish Environmental Protection Agency carried out test fishing
with nets at Hoburgs bank and Norra Midsjöbanken. The catch was dominated by
cod, flounder and turbot. Other species caught were shorthorn sculpin, herring,
sprat, plaice, eelpout, lumpfish and great sand eel (Naturvårdsverket, 2010).
According to the 2020 Swedish Red List, cod is deemed to be Vulnerable (VU), eel
is Critically Endangered (CR) and fourbeard rockling is Near Threatened (NT),
while the other species referred to are deemed to be of Least Concern (LC) (SLU
Artdatabanken, 2020).
Parts of Hoburgs bank och Midsjöbankarna, as well as Södra Midsjöbanken, are
considered to be spawning grounds for herring (see Figure 16), sprat, flounder,
plaice, turbot and eelpout. The planned offshore wind farm is located within
spawning grounds for herring. Part of the offshore banks may also provide nursery
areas for cod, flounder, plaice and eelpout. Salmon and sea trout may temporarily
be present in the affected areas as these are potential nursery and feeding
grounds (Marine Monitoring AB, 2022).
33 of 61
Figure 16. Illustration of spawning grounds for herring in the Baltic Sea and within
the project area (Marine Monitoring AB, 2022).
6.5.2 Possible impacts Temporary changes may occur in fish behaviour during the construction and
decommissioning phases due to turbidity, sedimentation and potential release of
pollutants into sediments. In a worst case scenario, sediment dispersion may
result in mortality as fish eggs are covered or suspended material becomes
trapped in the gills of the fish. The effect of sediment dispersion depends mainly
on the bottom substrate at the site: fine-grained sediment may cause more
extensive dispersion, for example.
Underwater noise during the construction and decommissioning phases has the
potential to affect fish as increased noise levels can result in flight behaviour and
affect their hearing, and – in a worst case scenario – cause mortality. The wind
farm will cause a change in the underwater soundscape in the affected area during
the operational phase.
The wind farm’s occupation of the affected seabed may affect fish habitats during
the construction phase. What is known as a reef effect may be formed as a result
of the addition of new solid structures such as hardground in the form of
foundations. A reef effect means that certain fish species are attracted to
structures and there is an increased abundance of them in the vicinity of the wind
turbines as the change provides a new habitat where fish can find food and seek
shelter. The numbers of fish accumulating has been shown to increase with the
structural complexity of the foundation (Naturvårdsverket, 2008). The reef effect
may disappear when the wind farm structures are decommissioned.
34 of 61
Shadowing from the stationary tower and rotating rotor blades may affect fish in
the vicinity during the operational phase.
Electromagnetic fields from power cables on the seabed may potentially affect the
spatial orientation of fish.
6.5.3 Delimitation The impact of the construction, operational and decommissioning phases on fish
will be further investigated and assessed in the forthcoming EIA.
6.6 Marine mammals
6.6.1 Baseline description Harbour porpoises (see Figure 17) and seals (grey seals, common seals and
ringed seals) are marine mammals that regularly inhabit the Baltic Sea. There are
Baltic harbour porpoises and grey seals in the Natura 2000 area of Hoburgs bank
och Midsjöbankarna (Länsstyrelsen Gotland län och Kalmar län, 2021).
The Baltic population of harbour porpoises is a toothed whale species of note for
the Natura 2000 area Hoburgs bank och Midsjöbankarna: see section 6.1.8. The
population in the area is present in higher densities in months when the animals
calve and mate (AquaBiota, 2016). The species is considered to have an
unfavourable conservation status in the Baltic Sea and is deemed to be Critically
Endangered (CR) (SLU Artdatabanken, 2020). Harbour porpoises are usually found
alone or in small groups, and are usually found in coastal areas close to the
surface of the water or at depths below 200 m. Harbour porpoises have well-
developed hearing and a wide frequency range, which results in a high sensitivity
to underwater noise (AquaBiota, 2016). The June to November period is an
important time for harbour porpoises when mating, birth and suckling of calves
take place. They are considered to be most sensitive to disturbance from June to
August (Naturens Stemme, 2022), and the June to September period is
biologically important for harbour porpoises (HELCOM, 2019). Harbour porpoises
mainly eat fish such as herring, cod, sprat, sandlances and gobies (AquaBiota,
2016). The area immediately west of Södra Midsjöbanken is not deemed to be a
main foraging area for harbour porpoises (Naturens Stemme, 2022). The company
commissioned a survey of harbour porpoises in the survey area for the wind farm
from February 2020 to December 2020 and January 2021 to December 2021
using harbour porpoise detectors. The results indicate that harbour porpoises do
not permanently reside in the area but occur more intermittently and demonstrate
seasonal variation, and occur at higher densities mainly during the summer
period. The area is not considered to be an important foraging area (BioConsult
SH, 2020; BioConsult SH, 2021).
35 of 61
Figure 17. Harbour porpoise abundance in the Baltic Sea during the May to October period (left) and the November to April period (right), measured during the SAMBAH project in 2011-2013 (SAMBAH, 2016).
The grey seal is deemed to be of Least Concern (LC) (SLU Artdatabanken, 2020)
and can be observed along most of the coast of Sweden, but it is more abundant
in the areas around the Stockholm archipelago and Åland. The species is
dependent on open water and usually remains further out from the coast, such as
at the outermost islets or skerries. Grey seals have well-developed hearing and a
wide frequency range, which makes them vulnerable to underwater noise. The
reproductive period falls in May-June, and for grey seals in the northern part of
the Baltic Sea, pups are usually born directly on the drift ice at the turn of the
month between February and March. Between summer and late autumn, grey
seals forage across large parts of the Baltic Sea at depths of 10-40 m. The species
is not specialised in its food selection, but feeds mostly on various shoaling and
bottom-dwelling fish such as herring, eelpout and flatfish, but also on salmonids,
cod and whitefish (SLU Artdatabanken, 2022; Thomsen, Ludemann, Kafemann, &
Piper, 2006). According to (Havs- och vattenmyndigheten, 2018), grey seals do
not reside permanently in the project area, but may be present from time to time.
6.6.2 Possible impacts During the construction phase, or during any decommissioning works, harbour
porpoises may be affected by underwater noise from piling works, which may
result in behavioural changes, flight behaviour or – in a worst case scenario –
mortality. The wind farm will cause a change in the underwater soundscape in the
affected area during the operational phase.
During the operational phase, any reef effect – see section 6.5.2 – may attract
fish to the area, which in turn may attract harbour porpoise and grey seal
individuals to the location.
36 of 61
6.6.3 Delimitation As harbour porpoises and grey seals may periodically occur in the project area,
the impact of the construction, operational and decommissioning phases on both
species will be further investigated and assessed in the forthcoming EIA.
6.7 Birds
6.7.1 Baseline description In the Baltic Sea, the breakdown of bird species varies according to the season,
with some occurring all year round and others staying more intermittently in the
area. The various locations in the Baltic Sea thus provide important sites for
foraging, breeding, rearing and wintering. As migratory birds usually migrate via
land areas or along the coastal strip, the incidence of birds flying longer distances
over the open sea is relatively low.
In the Baltic Sea, Hoburgs bank och Midsjöbankarna and Södra Midsjöbanken are
important wintering areas, mainly for long-tailed ducks and black guillemots, as
well as for common guillemots and razorbills. Black-throated divers, red-throated
divers, velvet scoters, eiders, common scoters, black-headed gulls, common gulls,
European herring gulls, lesser black-backed gulls and great black-backed gulls
may also be present in the areas concerned (Ottvall Consulting AB, 2021b;
Länsstyrelsen Gotland län och Kalmar län, 2021).
Aerial surveys of sea birds in the Baltic Sea were carried out in 2009-2011, 2016
and the 2019/2020 and 2020/2021 winter periods. In Södra Midsjöbanken, an
inventory of black guillemots was also carried out from a boat. Long-tailed ducks
dominated in numbers during the period in question. Long-tailed ducks and black
guillemots were mainly found in the shallower parts of Södra Midsjöbanken.
Common guillemots and razorbills were mainly found in the deeper parts.
Common gulls, European herring gulls, great black-backed gulls, little gulls,
common scoters, velvet scoters, red-throated divers and black-throated divers
were observed in varying numbers. The results indicate that Södra Midsjöbanken
is an important winter foraging area for long-tailed ducks and black guillemots in
the main, as well as for common guillemots and razorbills. (Ottvall Consulting AB,
2021a).
According to the 2020 Swedish Red List, the long-tailed duck, black guillemot,
common gull and red-throated diver are deemed to be near threatened (NT) and
the European herring gull, great black-backed gull and velvet scoter are deemed
to be vulnerable (VU), while the other species observed in the study area are
deemed to be of least concern (LC) (SLU Artdatabanken, 2020).
Södra Midsjöbanken is deemed to be of no importance as a foraging area during
the breeding period, as the area is so far from the breeding sites that regular
flights to the area during the period are considered unlikely (Ottvall Consulting AB,
2021b). The project area is also not considered to be within a significant migratory
route for birds, as only a few bird species in low numbers are estimated to pass
through the project area (Ottvall Consulting AB, 2022).
37 of 61
BirdLife International has identified what are known as Important Bird and
Biodiversity Areas (IBAs) based on 20 criteria, including threatened species,
restricted-range species, species with unfavourable conservation status and large
congregations of birds (including migratory species) (BirdLife Sverige, 2021).
Södra Midsjöbanken is designated by BirdLife International as an Important Bird
and Biodiversity Area (IBA) with respect to large populations of black guillemots
and long-tailed ducks in winter: see Figure 18.
Figure 18. Important Bird Areas (IBA) at the planned wind farm (BirdLife Sverige,
2021).
6.7.2 Possible impacts During the construction and decommissioning phases, birds remaining in the area
such as when foraging may be temporarily affected indirectly or directly by
activities causing turbidity or noise. The presence of project-related vessels may
also have an impact.
During the operational phase, the wind turbines may constitute obstacles for birds
which, in the event of collision, may lead to mortality. The barrier effect may lead
38 of 61
to a change in the feeding patterns of the birds concerned and their passage
through the area.
6.7.3 Delimitation As birds periodically occur in the project area and may be affected by the wind
farm, impacts of the construction, operational and decommissioning phases will be
further investigated and assessed in the forthcoming EIA.
Any impact on the IBA area will be further investigated in the forthcoming EIA.
6.8 Bats
6.8.1 Baseline description 19 bat species have been found in Sweden, and there is wide variation in how the
species are distributed geographically throughout the country and how they
behave. Several species migrate in autumn and spring, but only a few species are
generally thought to move around. Bats can also hunt over the sea, although they
do not make migratory flights over the sea, as has been observed in several
locations. Studies show that migratory species congregate at specific outbound
points in autumn and wait for good weather conditions before flying over the sea,
but otherwise follow the land and coast as far as possible. There is also migration
of bats in spring (Calluna, 2021).
In the case of bat migration, for example, the common noctule, soprano
pipistrelle, Nathusius’ pipistrelle, serotine bat, northern bat, pond bat and
Daubenton’s bat have been reported at sea (Calluna, 2021). Most of these
sightings were closer to the coast than the project area. However, a previous
survey at Södra Midsjöbanken shows that the bats pass over the open sea and
that at least two species, the Nathusius’ pipistrelle and the parti-coloured bat,
both of which are known long-distance migrants, have been found at Södra
Midsjöbanken (Eriksson et al., 2013; Calluna, 2021). The closest coastline from
the project area is the Öland coast, about 70 km away. The occurrence of bats is
therefore expected to be relatively limited in the project area.
All bat species are protected under Section 4 of the Species Protection Ordinance,
which means a general ban on deliberately capturing, killing, harming or
disturbing the animals. The prohibition in the Species Protection Ordinance also
includes damage to animal habitats. Several species are red-listed according to
the Swedish Red List, such as the pond bat, serotine bat and northern bat, which
are listed as ‘near threatened’, and the lesser noctule and common pipistrelle,
which are listed as ‘vulnerable’ (SLU Artdatabanken, 2020).
6.8.2 Possible impacts Bats can potentially be affected by the wind farm mainly during operation by
collision with the wind turbine blades, or by being caught in a wind current and
sucked behind the blades, resulting in a pressure drop that can cause internal
bleeding in bats. The risk of bats being affected by wind turbines varies between
species. Among the high-risk species to be affected by the wind turbines are those
that hunt insects over large open areas and those that may have their migration
39 of 61
routes past the project area. Bats can stop and examine wind turbines out at sea
and in the absence of other structures, wind turbines can be particularly attractive
for bats to use for resting during a long flight over the Baltic Sea (Calluna, 2021).
6.8.3 Delimitation As bats may occur in the project area and may potentially be affected by the
planned wind farm, impacts of the construction, operational and decommissioning
phases on bats will be further investigated and assessed in the forthcoming EIA.
6.9 Cultural environment and marine archaeology
6.9.1 Baseline description As humans have been travelling on the Baltic Sea for about 10,000 years, traces
of cultural history may still be present under the surface of the sea. These remains
include wrecks, buildings or historically important environments such as
settlements. The Baltic Sea has been, and still is, a well-travelled sea that hides
many wrecks on the seabed from different historical periods. The absence of
shipworm in the Baltic Sea has also meant that many of these wrecks have been
preserved over the years (Vrak, 2021).
According to the Cultural Environment Act, remains from before 1850 are
considered ancient remains. There are no known cultural historical remains within
the project area: see Figure 19.
40 of 61
Figure 19. Cultural historical remains at the project area (Riksantikvarieämbetet, 2022).
6.9.2 Possible impacts A marine archaeological survey will be carried out in the project area at a later
stage to ascertain the presence and nature of any remains in the area. Any
remains found will be avoided so as to avoid possible impacts, and protective
measures will be observed during the construction, decommissioning and
operational phases.
6.9.3 Delimitation A marine archaeological survey will be carried out in the project area at a later
stage. Protective measures and consequences of the construction, operational and
decommissioning phases for any marine archaeological remains will be further
investigated and assessed in the forthcoming EIA.
41 of 61
6.10 Outdoor recreation
6.10.1 Baseline description The project area is not covered by any national interest for outdoor recreation.
However, the sea is important for human well-being and quality of life and thus for
outdoor recreation, which provides opportunities for recreational activities such as
fishing, boating and diving. Outdoor recreation includes experiences linked to the
cultural environment, such as wreck diving, or the natural environment such as
protected marine areas.
6.10.2 Possible impacts The wind farm will produce two types of noise during the operational phase:
mechanical (including the gearbox in the hub) and aerodynamic (the movement of
the rotor blades through the air). The project area is located about 70 km south of
the coast of Öland, which means that the distance is so great that it is most likely
only passing boats will be able to perceive the change in sound and the experience
of a changed landscape in the area.
During the construction and decommissioning phases, vessels connected to the
project will operate in the affected area, which may affect the accessibility of other
boats. Safety zones will be ensured for the wind turbines, as well as for some
associated project vessels, during all three project phases.
The majority of recreational boats will not be affected by the project in the
affected area as they are mainly located closer to the coast.
6.10.3 Delimitation Impacts on outdoor recreation will be further investigated and assessed in the
forthcoming EIA.
6.11 Human health
6.11.1 Baseline description Wind farms can generate noise and shadows that can affect human health. The
project area is located in open water, about 70 km south of the coast of Öland.
6.11.2 Possible impacts The wind farm will produce two types of noise during the operational phase:
mechanical (including the gearbox in the hub) and aerodynamic (the movement of
the rotor blades through the air). As the wind farm is located at a great distance
from Öland, no homes will be affected by airborne noise during the operational
phase.
During the operational phase, the wind farm will generate both stationary and
moving shadow effects from the towers and the rotating rotor blades. No dwellings
will be affected by the shadow effects of the project area as there is a great
distance from the wind farm to the nearest dwellings, which are located on Öland.
42 of 61
6.11.3 Delimitation The impact of the wind farm on human health will not be addressed further in the
forthcoming EIA, as there is a great distance from the nearest coast to the project
area.
6.12 Shipping and fairways
6.12.1 Baseline description The traffic routes on the sea that are usually marked with solid black lines on
charts are known as fairways. The Swedish Maritime Administration is responsible
for accessibility, availability and safety in Swedish coastal waters for infrastructure
at sea (development and maintenance).
The fairways through Hoburgs bank och Midsjöbankarna are both extensive and
used by various types of vessels, including fishing boats, passenger vessels,
tankers and cargo vessels. Vessel traffic also occurs outside designated fairways
(Sweco, 2022b).
There is a main fairway to the north of the project area, at its closest point about
8 km away, which is mainly used by large vessels such as cargo, tanker and
passenger vessels. There is a small fairway to the south-west of the site, about 7
km away, which is mainly used by passenger, unidentified and cargo vessels.
Around 900 vessels passed through the planned wind farm area, mainly cargo
vessels and unidentified vessel types, between 2020 and 2021. According to the
Swedish Maritime Administration’s reporting system for AIS information, about
42,000 vessels passed between Öland and Södra Midsjöbanken in 2015. There is
also extensive shipping south of Södra Midsjöbanken. Another main fairway runs
about 40 km north-west of the project area (Sweco, 2022b).
43 of 61
Figure 20. Illustration of vessel traffic (AIS data) inside and outside the project area between May 2020 and April 2021. The green line indicates northbound traffic, and the orange line indicates southbound traffic. © Swedish Maritime Administration permit no 21-02646.
6.12.2 Possible impacts Different types of vessels related to the project will operate in the area of the
planned wind farm during the construction and decommissioning phases, and this
could affect nearby shipping.
Safety zones will be ensured for project-related vessels during the construction
and decommissioning phases, as well as during the operational phase for any
repairs or maintenance within the wind farm. During the operational phase, a
safety zone will be established around the wind turbines, including during the
construction and decommissioning of structures that could affect shipping.
An impact on boats sailing outside existing fairways cannot be excluded, as the
wind farm constitutes a more or less permanent obstacle to maritime traffic in
part of the area during the operational phase.
6.12.3 Delimitation The impact of the construction, operational and decommissioning phases on
shipping and fairways will be further investigated and assessed in the forthcoming
EIA.
44 of 61
6.13 Commercial fishing
6.13.1 Baseline description According to the Marine Plan, the western part of Hoburgs bank och
Midsjöbankarna (area Ö245) is designated as a commercial fishing area. The
planned wind farm is outside the national interest area for commercial fishing: see
section 6.1.6.
In the project area and neighbouring sub-areas, commercial fishing is carried out
mainly by countries such as Sweden, Poland, Denmark, Latvia, Estonia and
Lithuania (Marine Monitoring AB, 2022) Herring and sprat are two of the species
with the highest EU quotas in the Baltic Sea (Havs- och vattenmyndigheten,
2022e). The herring in the project area forms part of the central Baltic Sea stock,
excluding the Gulf of Riga. Sweden accounted for the largest share of catches in
2020 with 26%, followed by Poland and Finland, which accounted for around 20%
and 18% of catches respectively. For sprat, Sweden accounted for only 15% of
Baltic catches in 2020 (Havs- och vattenmyndigheten, 2022a).
Swedish commercial fishing takes place both along the coast and out at sea and
consists mainly of smaller fishing boats but also a smaller number of larger
vessels. The fishing method varies according to the size and type of vessel, the
species of fish and whether the area is coastal or offshore. In general nets, pots,
cages, trawls and pelagic fishing gear are used (Marine Monitoring AB, 2022).
Swedish commercial fishing takes place to a large extent south of the planned
wind farm and consists almost exclusively of trawling. The proportion of recorded
catches is lower in the Natura 2000 area compared to neighbouring sites. There is
a small amount of trawling to the west of the area, and a small amount of net
fishing just to the east of the area, within Södra Midsjöbanken. In the project
area, there have been only a small number of registrations for trawling and net
fishing. Trawl catches consisted mainly of sprat and herring, but also cod. The
catches in nets consisted mainly of cod and turbot, but flounder, plaice and
mackerel were also present. In the areas around the planned wind farm, the total
catch weight for the years 2015-2019 consisted of 87% herring and sprat, 9% cod
and 2% flounder (Marine Monitoring AB, 2022).
6.13.2 Possible impacts During the construction, decommissioning and operational phases, access to
certain locations within the project area may need to be restricted as this poses a
safety risk: see section 6.12. Restrictions may be placed on different fishing
methods as the project will change the conditions for commercial fishing in the
project area.
During the construction and decommissioning phases, turbidity and possible
release of contaminants from sediments into the water may affect water quality.
This may cause behavioural changes in fish, which may indirectly affect their
tendency to be caught.
45 of 61
Underwater noise associated with the construction and decommissioning phases
can also cause behavioural changes in fish, potentially affecting their tendency to
be caught.
6.13.3 Delimitation The impact of the construction, operational and decommissioning phases on
commercial fishing will be further investigated and assessed in the forthcoming
EIA.
6.14 Military areas
6.14.1 Baseline description The planned wind farm is not located in any openly declared area of national
interest within the military component of total defence: see section 6.1.5. About
11 km south of the project area is a designated military area for underwater
exercises for Germany, Denmark and Sweden (EMODnet, 2022): see Figure 21.
Information on military interests in the area is expected to be highlighted during
the consultation process.
Figure 21. Military areas around the planned wind farm (EMODnet, 2022).
46 of 61
6.14.2 Possible impacts The project area is not located within any openly designated training area.
Potential impacts may occur during the construction and decommissioning phases
for those national interests for total defence that are not declared in the area.
Project-related shipping may then pose an obstacle to any military exercises that
may be carried out in the area during the construction and decommissioning
phases. The offshore wind farm is a permanent structure in the area during the
operational phase, which may affect possible military activities.
6.14.3 Delimitation The impact of the construction, operational and decommissioning phases on
military interests and possible coexistence between stakeholders will be further
investigated and assessed in the forthcoming EIA.
6.15 Infrastructure
6.15.1 Baseline description Offshore wind farms, cables, pipelines, aviation and even airborne radio signals
may be present within and in the vicinity of the planned wind farm.
Nord Stream and Nord Stream 2 are two natural gas pipelines located about 25
km from the project area. NordBalt is a submarine cable for heavy current located
about 4 km north of the wind farm area (EMODnet, 2022; TeleGeography, 2022;
HELCOM, 2022).
There is active sand mining activity at Södra Midsjöbanken, within the Polish
Economic Zone.
The nearest offshore wind farm is Kårehamn, located about 140 km north of Södra
Victoria. Arkona, Wikinger and Kriegers flak are offshore wind farms located about
200 km south-west of Södra Victoria in the German and Danish Economic Zones
(4coffshore, 2022; EMODnet, 2022; Länsstyrelserna, 2022).
47 of 61
Figure 22. Infrastructure around the planned wind farm (EMODnet, 2022; HELCOM, 2022; Länsstyrelserna, 2022).
6.15.2 Possible impacts Existing cables or pipelines on the seabed may be damaged during the
construction and decommissioning phases if protective measures are not taken.
The possibility of maintenance on existing cables or pipelines may be temporarily
limited within the project area during the construction and decommissioning
phases. Any structures left behind during the removal of the wind farm may affect
planned installations.
Airborne radio signals may be affected by the wind farm, including both
transmission and reception of signals.
The wind farm represents a series of new structures at sea, so it may pose a
safety risk to aviation, such as collision risk. There is a great distance to the
nearest wind farms, so no impact from the planned wind farm is expected.
48 of 61
6.15.3 Delimitation The impact of the construction and decommissioning phases on infrastructure will
be further investigated and assessed in the forthcoming EIA. Relevant authorities
and activities will be consulted for radio signals and aviation. Flight obstacle
analysis will be developed at a later stage.
6.16 Monitoring stations
6.16.1 Baseline description Environmental monitoring stations for the Kust och hav [Coast and Sea] national
environmental monitoring programme are located around the planned wind farm
(Havs- och vattenmyndigheten, 2022). National environmental monitoring is
governed by set environmental objectives, legislative requirements, EU directives
and Sweden’s commitments under international conventions. There are also
environmental monitoring stations for hydroacoustics and trawling coordinated
through the International Council for the Exploration of the Sea (ICES). These
surveys are carried out within ICES statistical rectangles, which may mean that
the location of the survey may vary within the rectangle from one year to the next
(ICES, 2014a; 2014b). ICES coordinates marine and coastal monitoring and
research and advises commissions and authorities on management issues (Havs-
och vattenmyndigheten, 2022c). No environmental monitoring stations are located
within the planned wind farm. The closest environmental monitoring station that
has had regular sampling (between 2017-2020) is station 1026, which surveys the
presence of harbour porpoises. This station is located about 27 km from the
planned wind farm.
6.16.2 Possible impacts During construction and decommissioning of the planned wind farm, turbidity,
sedimentation and possible release of pollutants will occur in the water mass
which could potentially affect environmental monitoring stations. During
construction, operation and decommissioning, underwater noise is generated
which could potentially affect hydroacoustic measurements.
6.16.3 Delimitation The impacts of the construction, operational and decommissioning phases will be
further investigated and assessed in the forthcoming EIA.
6.17 Raw material extraction sites
6.17.1 Baseline description Raw material extraction sites aim to extract sand or gravel from the seabed.
Södra Midsjöbanken offers opportunities for extraction of postglacial sand and
gravel. However, sand extraction is probably not possible as the area consists of
valuable ecosystems, and sand extraction is directed to other possible areas
according to the Marine Plan. Extraction of raw materials is not possible at
Hoburgs bank och Midsjöbankarna (SGU, 2015).
There is currently no carbon dioxide storage in the seabed in Sweden, but in
general, carbon dioxide is stored mainly on sedimentary bedrock, making the
south-eastern Baltic Sea a suitable area for possible carbon dioxide storage. The
49 of 61
potential storage units in the south-eastern Baltic Sea are Faludden, När and
Viklau. The project area is located within the potential areas for carbon dioxide
storage (SGU, 2016).
6.17.2 Possible impacts The planned wind farm may pose a future obstacle in the area to possible
extraction of sand or gravel in Södra Midsjöbanken and carbon dioxide storage on
part of the seabed in south-eastern Baltic Sea storage units.
6.17.3 Delimitation As the designated area for extraction of raw materials in Södra Midsjöbanken is
not likely to be feasible, this will not be addressed further in the forthcoming EIA.
The impact of the planned wind farm on carbon dioxide storage will be further
investigated and assessed in the forthcoming EIA.
7. Landscape view
The visual impact of a wind farm depends on the design of the wind farm, the
dimensions of the wind turbines, the distance, the vantage point and the weather
conditions. The wind farm will not be visible from land because of the large
distance from land to the planned wind farm, which is at least 70 km from the
southern tip of Öland.
During the operation of the planned wind farm, the wind turbines will be equipped
with what is known as obstruction lighting so that they are visible even in the dark
out of consideration for the safety of aviation and shipping. The wind turbines will
be obstruction marked for aviation navigation purposes in accordance with the
Swedish Transport Agency’s regulations on obstruction lighting in TSFS 2020:88.
They will also be marked with maritime safety devices and markings for shipping
in the form of lights on the foundations or the lower part of the tower for shipping,
for example, in accordance with the Swedish Transport Agency’s regulations TSFS
2017:66. The transformer substation will also be marked during the operation of
the planned wind farm.
The impact of the planned wind farm on the landscape will not be investigated
further due to the long distance to land.
8. Marine Environment Directive and Water Framework
Directive
8.1 Marine Environment Directive The Marine Environment Directive is implemented in Swedish law through Chapter
5 of the Environmental Code and in the Marine Environment Ordinance
(2010:1341) and the Swedish Maritime and Water Agency’s Code of Statutes
(HVMFS) 2012:18. The Directive aims to achieve or maintain good environmental
50 of 61
status in the seas of Europe. Environmental quality standards (EQS) for the
marine environment are used as legal instruments in order to maintain good
environmental status.
8.1.1 Good environmental status Good environmental status is characterised by 11 descriptors: see Table 3, in
Annex 2 to HVMFS 2012:18. The conditions under which good environmental
status is achieved are described by the criteria of each descriptor. Indicators must
be provided for each criterion (some are missing) that specify what is being
measured/studied in the environmental monitoring in order to assess compliance
with the criterion.
Table 3. The eleven descriptors of good environmental status.
Good environmental status
Descriptor 1. Biodiversity
Descriptor 2. Non-indigenous species
Descriptor 3. Commercially exploited fish and shellfish
Descriptor 4. Marine food webs
Descriptor 5. Eutrophication
Descriptor 6. Sea floor integrity
Descriptor 7. Permanent alteration of hydrographical conditions
Descriptor 8. Concentrations and effects of hazardous substances
Descriptor 9. Hazardous substances in fish and other marine foods
Descriptor 10. Marine litter
Descriptor 11. Underwater noise
The planned wind farm is located within the offshore waters of the Bornholm Sea
and Hanöbukten. Possible impacts on the descriptors and thus on the good
environmental status of the marine environment will be addressed in more detail
in the EIA.
8.1.2 Environmental quality standards for the marine environment EQSs have been defined for the marine environment in order to achieve good
environmental status. These can be sorted according to the five environmental
pressures shown in Table 4. Annex 3 to HVMFS 2012:18 contains EQSs for the
marine environment. Each EQS must have at least one indicator (some lack
additional indicators). Indicators are used in environmental monitoring
measurements/surveys in order to assess compliance with EQSs.
51 of 61
Table 4. Five environmental pressures under which the various EQSs are classified.
Environmental pressures
A. Supply of nutrients and organic matter
B. Supply of hazardous substances
C. Biological disturbance
D. Physical disturbance
E. Litter and noise
Any impact on EQSs for the marine environment will be addressed in more detail
in the EIA.
9. Risk analysis
The company will include a risk analysis in the EIA to identify risks to shipping and
the area’s natural assets during construction, operation and decommissioning of
the Södra Victoria wind farm. This analysis also includes unplanned emissions in
the event of an accident and proposals for risk-mitigating measures. The analysis
will be based on the risk analysis included in the company’s application for a
Natura 2000 permit for the wind farm. The following main conclusions can be
drawn on the basis of the risk analysis:
• The Södra Victoria wind farm is not expected to cause a major increase in
risk in the area.
• The risk to shipping is not expected to increase significantly as a result of
the wind power installation. A small number of vessels that currently pass
through the planned wind power area will have to change course. The
crowding together of shipping caused by the wind farm is estimated to be
small.
• The risk to conservation values in the area increases slightly as a result of
a wind power installation at Södra Midsjöbanken. The consequences of an
accident resulting in an oil spill could be serious. However, the probability
of such an accident occurring is low.
• There are always certain risks associated with the establishment of a wind
farm, as the wind farm will create a new potential obstacle to maritime
traffic. Risk mitigation measures should therefore be taken.
Risk analysis and mitigation measures will be further described in the EIA.
52 of 61
10. Cumulative effects
Potential cumulative effects on the environment and the surrounding area may
occur as a result of the company’s planned activities in combination with other
wind farms and other activities in the area.
According to Section 18 of the Environmental Assessment Ordinance (2017:966),
cumulative effects arising from the proposed activity in combination with other
activities that are currently carried out, have received a permit, or have been
notified and may be commenced must be reported.
Ongoing activities in the maritime area with which the planned activities could
potentially give rise to cumulative effects include shipping and mining activities in
the Polish Economic Zone at Södra Midsjöbanken. The company is not aware of
any licensed wind farms or other licensed or notified activities in the south-eastern
Baltic Sea that may have cumulative effects together with Södra Victoria.
Cumulative effects will be investigated and described in the forthcoming EIA.
11. Surveys and investigations
Various surveys and investigations will form the basis for the assessments carried
out for the forthcoming EIA. Further surveys and investigations may be carried out
if issues arise during the consultation that have not been considered previously.
These issues will then be developed in the EIA. The company’s completed and
planned surveys are presented below.
11.1 Completed RWE has extensive knowledge of the area and the environment in and around the
planned Södra Victoria wind farm from the company’s history of establishing
offshore wind power in Södra Midsjöbanken: see section 1.2. The surveys that
have been carried out for the planned Södra Victoria wind farm and that will form
the basis of the forthcoming EIA are presented below.
Alternative locations:
SWECO, 2022. Investigation of alternative locations for offshore wind farms.
Underwater noise:
Ramboll, 2020. Södra Victoria offshore wind farm. Part 1. Modelling of underwater
noise from geotechnical survey equipment.
Ramboll, 2021. Södra Victoria offshore wind farm. Part 2. Modelling of underwater
noise.
Sediment dispersion:
SWECO, 2022. Sediment dispersion during wind farm construction and cable
laying – Södra Victoria project.
53 of 61
Bottom flora and fauna:
Ocean Ecology, 2022. Södra Victoria Offshore Wind Farm Benthic Characterisation
Survey 2021.
Fish and commercial fishing:
Marine Monitoring AB, 2022. Södra Victoria – Impact on fish communities and
commercial fishing.
Marine Monitoring AB, 2020. Investigation of pelagic fish in Södra Midsjöbanken
and their importance as a food source for harbour porpoises and sea birds.
Harbour porpoises:
Naturens Stemme, 2022. Possible impact of the offshore Södra Victoria wind farm
at Södra Midsjöbanken on the Baltic harbour porpoise.
BioConsult SH, 2021. Södra Victoria C-POD monitoring. Presence of harbour
porpoises (Jan.2020 – Dec. 2020).
BioConsult SH, 2022. Södra Victoria (formerly Södra Midsjöbanken). C-POD
monitoring. Presence of porpoises (Jan.2021 – Dec. 2021).
Birds
Ottvall consulting AB, 2022. Birds at Södra Midsjöbanken Occurrence of birds in
relation to planned wind power.
Ottvall consulting AB, 2021. Use of Södra Midsjöbanken by breeding bird
populations.
Ottvall consulting AB, 2022. Migratory birds at Södra Victoria in relation to
planned wind power.
Bats:
Calluna, 2021. Desk study on bats at Södra Midsjöbanken 2021 – Possible impact
on bat fauna from the planned wind farm on the basis of similar previous surveys.
Risk analysis:
SWECO, 2021. Risk analysis for wind power installation at Södra Midsjöbanken.
11.2 Planned Geophysical and geotechnical surveys, including drilling, will be carried out and
used as a basis for the detailed design of the planned wind farm, the final
selection of foundation techniques and the selection of cable laying methods in the
area of the wind farm and the cable corridor for the export cable. Permits for
these surveys will be examined in a separate exercise at a later stage.
54 of 61
A marine archaeological survey will be carried out at a later stage within the
planned wind farm to ascertain the possible presence and type of remains in the
area.
12. Ongoing process
12.1 Schedule for the planned activities Provided that the necessary permits are obtained, the preliminary schedule for
construction, operation and decommissioning is expected to be as follows:
• Pre-construction surveys: approx. 1 year
• Construction work: approx. 2–4 years
• Operation: min. approx. 35 years
• Decommissioning: 1–2 years
12.2 Timetable for the permit process Figure 23 shows an example timetable for the permit process for review in
accordance with the Swedish Economic Zone Act and the Continental Shelf Act,
the reviews that are considered to be design factors for the schedule. The timing
of the various permit processes and their mutual order are not definite. The permit
processes are estimated to take a total of three to four years before the
construction phase can begin.
Figure 23. Example of a schematic schedule for the review process for a wind farm
in the Swedish Economic Zone.
12.3 Continued consultation process and reviews Before the wind farm is established, further consultations will be carried out with
relevant stakeholders and authorities after the current delimitation consultation
has been completed.
12.4 Adjustments during the EIA process As the consultation and EIA process proceeds, during which the conditions for
relevant aspects will be identified, it will be possible to make an early analysis of
the project’s expected environmental impact and gain an overall picture of its
consequences. This will provide a basis for progressively planning and designing
adjustments and protective measures in the project. The environmental
Consultation process
EIAs and technical description produced
Applications and EIAs sent to the
Government Update procedure
Announcement Consultation
procedure Decision by the
Government Start of
construction
55 of 61
adaptation carried out in the project through the environmental assessment
process will be described as a whole in the EIA document.
13. Content of the environmental impact assessment and
parties to be consulted
13.1 Delimitation of the environmental impact assessment Chapter 6, Section 35 of the Environmental Code states what an EIA must include.
The information to be included in an EIA must be of a scope and level of detail
that is reasonable in the light of current knowledge and assessment methods and
which is necessary to provide an overall assessment of the significant
environmental effects that the activity or measure is likely to have (Environmental
Code, Chapter 6, Section 37).
Table 5 summarises the delimitation proposed in Chapter 6.
Table 5. Proposed delimitation in the forthcoming EIA.
Aspect Addressed in EIA Comments
National interest: wind
energy
Yes
National interest:
nature conservation
and nature reserves
Presentation of baseline
conditions only
National interest:
cultural environment
Presentation of baseline
conditions only
National interest:
outdoor recreation
Presentation of baseline
conditions only
National interest: total
defence
Depending on the
outcome of the
consultation process
National interest:
commercial fishing
Yes
National interest:
shipping and fairways
Yes
Natura 2000 Presentation of baseline
conditions only
Natura 2000 assessment
for Hoburgs bank och
Midsjöbankarna is a
separate process. Long
distance to other Natura
2000 areas
International protection Yes
Depth conditions and
hydrology
Presentation of baseline
conditions only
Seabed conditions,
sediments and pollution
Presentation of baseline
conditions only
56 of 61
Aspect Addressed in EIA Comments
Bottom flora and fauna Yes
Fish Yes
Marine mammals Yes
Birds Yes
Bats Yes
Cultural environment
and
marine archaeology
Yes
Outdoor recreation Yes
Human health No Long distance to the coast
Shipping and fairways Yes
Commercial fishing Yes
Military areas Depending on the
outcome of the
consultation process
Infrastructure Yes
Monitoring stations Yes
Raw material extraction
sites
Yes Carbon dioxide storage
only
Landscape view No Long distance to the coast
Marine Environment
Directive and Water
Framework Directive
Yes
Risk analysis Yes
Cumulative effects Yes
RWE proposes the following structure and content for the EIS through the
proposed delimitation:
Non-technical summary
1. Administrative details
2. Introduction
3. Permit process and environmental assessment
4. Consultation
5. Delimitation
6. Options
7. Technical description
8. Location, planning conditions and national interests
9. Method for assessments
10. Impacts of planned activities
11. Baseline description, environmental impact and protective measures during
construction, operation and decommissioning
11.1. Bathymetry
11.2. Water quality and hydrography
11.3. Sediments and pollutants in sediments
11.4. Wind conditions
57 of 61
11.5. Soundscape
11.6. Bottom flora and fauna
11.7. Fish
11.8. Marine mammals
11.9. Birds
11.10. Bats
11.11. Protected natural areas
11.12. Heritage sites
11.13. Recreation and outdoor activities
11.14. Commercial fishing
11.15. Shipping and fairways
11.16. Installations and infrastructure
11.17. Military training areas
12. Cumulative effects
13. Transboundary impacts
14. Risk assessment
15. Climate and air emissions
16. Marine Environment Directive
17. Environmental objectives
18. Overall assessment
19. Protective measures
20. Competence in the EIA team
References
During the consultation, RWE welcomes comments on the forthcoming EIA scope
and format.
13.2 Parties consulted RWE proposes that the following individuals, authorities, organisations and others
be included in the consultation and contacted by email or post:
State and local authorities
National Board of Building, Planning
and Housing
Swedish Environmental Protection
Agency
Swedish Energy Agency Swedish Police Authority
National Defence Radio Establishment
Swedish Post and Telecom Authority
(companies with radio and
telecommunications connections)
Swedish Armed Forces Region Gotland
Swedish Agency for Marine and Water
Management Swedish National Heritage Board
Swedish Board of Agriculture Swedish Geotechnical Institute
Legal, Financial and Administrative
Services Agency Swedish Maritime Administration
Municipality of Kalmar SMHI
Municipality of Karlskrona
Swedish National Maritime and
Transport Museums
Swedish Coast Guard Svenska Kraftnät
58 of 61
Swedish Civil Aviation Administration Geological Survey of Sweden
Kalmar County Administrative Board Municipality of Torsås
Gotland County Administrative Board Swedish Defence Research Agency
Swedish Civil Contingencies Agency Swedish Transport Administration
Municipality of Mörbylånga Swedish Transport Agency
Swedish Museum of Natural History
Associations and organisations
3G Infrastructure Services AB (3GIS) Swedish Pelagic Federation
Producentorganisation (SPFPO)
BirdLife Sweden Svenska Båtunionen
Coalition Clean Baltic Svenska kryssarklubben
Föreningen Svensk Sjöfart Svenska UMTS Nät AB
Greenpeace Sveriges fiskares
Producentorganisation (SFPO)
Havs- och kustfiskarnas
producentorganisation (HKPO)
Association Ports of Sweden
Hi3G Access AB Chamber of Commerce and Industry of
Southern Sweden
Kalmar Airport Tele 2
Swedish Society for Nature
Conservation.
Telenor
Net 4 mobility Telia
Rönne Airport Teracom
Ronneby Airport Visby Airport
Swedish Anglers Association World Wide Fund for Nature WWF
Swedavia
Miscellaneous
Swedish Institute for the Marine
Environment
Kalmar Maritime Academy
Lund University Stockholm University Baltic Sea Centre
Swedish University of Agricultural
Sciences
World Maritime University
Otherwise, the public and other stakeholders will be consulted via advertisements
in the daily press.
14. References
4coffshore. (den 20 06 2022). 4C Offshore. Hämtat från
https://map.4coffshore.com/offshorewind/ AquaBiota. (2016). Skyddsvärda områden för tumlare i svenska vatten.
BioConsult SH. (2020). Södra Victoria, C-POD övervakning, Förekomst av tumlare.
BioConsult SH. (2021). Södra Victoria (former: Södra Midsjöbanken, C-POD
Deployment, Harbour porpoise abundance.
59 of 61
BirdLife Sverige. (den 7 september 2021). IBA (Important Bird and Biodiversity
Areas). Hämtat från https://birdlife.se/fagelskydd/iba/
Calluna. (2021). Skrivbordsstudie om fladdermöss vid Södra Midsjöbanken 2021 -
Möjlig påverkan på fladdermusfaunan från planerad vindkraftsanläggning
med utgångspunkt från liknande tidigare undersökningar.
EEA. (2022). Natura 2000 data. Hämtat från European Environment Agency:
https://www.eea.europa.eu/data-and-maps/data/natura-13
EMODnet. (den 20 06 2022). Human activities. Hämtat från
https://www.emodnet-humanactivities.eu/view-data.php
Energimyndigheten. (den 21 juni 2022). Riksintressen energiproduktion -
vindbruk. Hämtat från
http://www.energimyndigheten.se/fornybart/riksintressen-for-
energiandamal/riksintressen-for-vindbruk/
Eriksson et al. (2013). Studie av migrerande fladdermöss vid Södra Midsjöbanken,
hösten 2012. - unpublished report to E.ON Vind Sverige AB.
Försvarsmakten. (2020). Riksintressen. Hämtat från
https://www.forsvarsmakten.se/sv/information-och-fakta/forsvarsmakten-
i-samhallet/samhallsplanering/riksintressen/ den 1 juli 2021
Havs- och vattenmyndigheten. (2018). Faktablad för att bedöma god miljöstatus
enligt havsmiljöförordningen, 1.4A Utbredning av gråsäl.
Havs- och vattenmyndigheten. (2020). Förteckning över områden av riksintresse
för yrkesfiske enligt Miljöbalkens 3 kapitel och 5 §. Områden i havet,
inlandsvatten och fiskehamnar. Dnr 2244-18.
Havs- och vattenmyndigheten. (den 04 02 2020). Riksintresse för yrkesfisket.
Hämtat från https://www.havochvatten.se/data-kartor-och-
rapporter/kartor-och-gis/karttjanster/karttjanster-fran-oss/riksintresse-
for-yrkesfisket.html den 01 06 2022
Havs- och vattenmyndigheten. (den 17 juni 2022). Miljöövervakningens
programområde Kust och hav. Hämtat från
https://www.havochvatten.se/overvakning-och-
uppfoljning/miljoovervakning/organisation-och-
programomraden/miljoovervakningens-programomrade-kust-och-hav.html
Havs- och vattenmyndigheten. (2022a). Fisk- och skaldjursbestånd i hav och
sötvatten 2021. Rapport 2022:2. Göteborg: Havs- och
vattenmyndigheten.
Havs- och vattenmyndigheten. (2022b). Havsplaner för Bottniska viken, Östersjön
och Västerhavet - Statlig planering i territorialhav och ekonomisk zon.
Havs- och vattenmyndigheten. (den 17 juni 2022c). ICES (The International
Council for the Exploration of the Sea). Hämtat från
https://www.havochvatten.se/planering-forvaltning-och-
samverkan/program-projekt-och-andra-uppdrag/forskning/ices.html
Havs- och vattenmyndigheten. (den 10 Juni 2022d). Karta att utforska. Hämtat
från https://www.havochvatten.se/vagledning-foreskrifter-och-
lagar/vagledningar/havsplaner.html#
Havs- och vattenmyndigheten. (den 20 juni 2022e). Kvoter i Östersjön 2022.
Hämtat från https://www.havochvatten.se/fiske-och-handel/kvoter-
uppfoljning-och-fiskestopp/kvoter-och-fiskestopp/kvoter-i-ostersjon.html
60 of 61
HELCOM. (2019). Noise sensitivity of animals in the Baltic Sea. Baltic Sea
Environment Proceedings 167.
HELCOM. (den 7 september 2021). Marine Protected Areas. Hämtat från
https://helcom.fi/action-areas/marine-protected-areas/
HELCOM. (06 2022). HELCOM Map and Data Service. Hämtat från
http://maps.helcom.fi/website/mapservice/index.html
HELCOM. (2022). HELCOM MPAs. Hämtat från Helcom metadata catalogue:
https://metadata.helcom.fi/geonetwork/srv/eng/catalog.search#/metadat
a/d27df8c0-de86-4d13-a06d-35a8f50b16fa
ICES. (2014a). Manual for the Baltic International Trawl Surveys (BITS). Series of
ICES Survey Protocols SISP 7 - BITS.
ICES. (2014b). Manual of International Baltic Acoustic Surveys (IBAS). Series of
ICES Survey Protocols SISP 8 - IBAS.
Länsstyrelsen Gotland län och Kalmar län. (2021). Bevarandeplan för Natura
2000-området SE0330308 Hoburgs bank och Midsjöbankarna.
Länsstyrelsen Kalmar län. (2016). Bevarandeplan för Natura 2000-området
SE0330108 Ottenby NR och SE0330083 Ottenby.
Länsstyrelserna. (06 2022). LST Vindbrukskollen Vindkraftverk. Hämtat från
Vindbrukskollen: https://vbk.lansstyrelsen.se/
Marine Monitoring AB. (2022). Södra Victoria - Påverkan på fisksamhället &
yrkesfisket.
Naturens Stemme. (2022). Möjlig påverkan på Östersjötumlaren av den
havsbaserade vindkraftparken Södra Victoria vid Södra Midsjöbanken.
Naturvårdsverket. (2005). Riksintresse för naturvård och friluftsliv. Handbok med
allmänna råd för tillämpningen av 3 kap. 6 §, andra stycket, Miljöbalken.
Handbok: 2005:5 . Stockholm: Naturvårdsverket.
Naturvårdsverket. (2006). Inventering av marina naturtyper på utsjöbankar.
Rapport 5576.
Naturvårdsverket. (2008). Miljömässig optimering av fundament för havsbaserad
vindkraft.
Naturvårdsverket. (2010). Undersökning av utsjöbankar. Inventering, modellering
och naturvärdesbedömning. Naturvårdsverket Rapport 6385.
Naturvårdsverket. (den 21 juni 2022). Naturreservat – vanlig och stark
skyddsform. Hämtat från https://www.naturvardsverket.se/Var-
natur/Skyddad-natur/Naturreservat/
Ocean Ecology. (2022). Södra Victoria Offshore Wind Farm Benthic
Characterisation Survey 2021.
Ottvall Consulting AB. (2021a). Fåglar på Södra Midsjöbanken.
Ottvall Consulting AB. (2021b). Häckande fågelpopulationers utnyttjande av Södra
Midsjöbanken.
Ottvall Consulting AB. (2022). Flyttfåglar vid Södra Victoria i förhållande till
planerad vindkraft.
Riksantikvarieämbetet. (den 6 september 2021). Riksintressen för
kulturmiljövården. Hämtat från
https://www.raa.se/samhallsutveckling/riksintresse-for-kulturmiljovarden/
Riksantikvarieämbetet. (den 23 06 2022). Riksantikvarieämbetets öppna data.
Hämtat från Riksantikvarieämbetets öppna data:
61 of 61
https://www.raa.se/hitta-information/oppna-data-fran-
kulturmiljoregistret/
SAMBAH. (2016). FINAL Report, Covering the project activities from 01/01/2010
to 30/09/2015. Hämtat från http://www.sambah.org/SAMBAH-Final-
Report-FINAL-for-website-April-2017.pdf
SGU. (2015). Förutsättningar för utvinning av marin sand och grus i Sverige.
SGU. (2016). Koldioxidlagring i Sverige - sammanställning och resultat från
NORDICCS.
SGU. (den 09 06 2022). Maringeologi. Hämtat från Kartvisare:
https://apps.sgu.se/kartvisare/kartvisare-maringeologi.html
SLU Artdatabanken. (2020). Rödlistade arter i Sverige 2020. Uppsala: SLU.
SLU Artdatabanken. (den 20 06 2022). Gräsäl. Hämtat från Artfakta:
https://artfakta.se/artbestamning/taxon/halichoerus-grypus-100068
SMHI. (2012). Syreförhållanden i svenska hav, FAKTABLAD NR 56.
SMHI. (2018). Oxygen Survey in the Baltic Sea 2018 - Extent of Anoxia and
Hypoxia, 1960-2018). REPORT OCEANOGRAPHY No. 65. Hämtat från
https://www.smhi.se/polopoly_fs/1.147412!/Oxygen_timeseries_1960_20
18_final.pdf 06 2022
SMHI. (2020). Oxygen Survey in the Baltic Sea 2020 - Extent of Anoxia and
Hypoxia, 1960-2020. Report Oceanography No. 70. Hämtat från
https://www.smhi.se/polopoly_fs/1.169653!/Oxygen_Survey%20in%20th
e%20Baltic%20Sea%202020.pdf
SMHI. (den 11 maj 2022). Den extrema syrebristen i Östersjön fortsätter. Hämtat
från https://www.smhi.se/nyhetsarkiv/den-extrema-syrebristen-i-
ostersjon-fortsatter-1.169650
Sweco. (2022b). Riskanalys för vindkraftsetablering vid Södra Midsjöbanken.
Sweco. (2022c). Utredning av alternativa lokaliseringar för parkområde för
vindkraft till havs. 2022-05-18.
TeleGeography. (den 20 06 2022). Submarine Cable Map. Hämtat från
https://www.submarinecablemap.com/
Thomsen, F., Ludemann, K., Kafemann, R., & Piper, W. (2006). Effects of offshore
wind farm noise on marine mammals and fish.
Trafikverket. (2021). Riksintressen kartor. Hämtat från
https://riksintressenkartor.trafikverket.se/
Vrak. (2021). Vrak, Muesum of wrecks. Hämtat från Unika Östersjön:
https://www.vrak.se/sv/marinarkeologi/unika-ostersjon/
Paldiski mnt 96/ Tallinn 13522/ 626 2802/ [email protected]/ www.envir.ee/
Registrikood 70001231
Vastavalt nimekirjale
04.10.2022 nr 6-3/22/4312-2
Rootsi „Södra Victoria” meretuulepargi projekti
piiriülene keskkonnamõju hindamine
Vastavalt piiriülese keskkonnamõju hindamise konventsioonile (Espoo konventsioonile) on
Rootsi teavitanud Eestit Läänemerre kavandatavast „Södra Victoria” meretuulepargi projektist.
Arendaja RWE Renewables Sweden AB kavandab püstitada Rootsi majandusvööndis
1500–2000 MW koguvõimsusega meretuulepargi, milles oleks maksimaalselt 100 tuulikut
maksimumkõrgusega 295 meetrit. Kirjale on lisatud ingliskeelne projekti ja selle elluviimisega
kaasnevat keskkonnamõju kirjeldav nn konsultatsioonidokument. Täiendavalt toome välja, et
varasemalt on arendaja (endise nimega E.ON Wind Sweden AB) kavandanud Södra Midsjöbanken
meretuulepargi projekti.
Lähtuvalt Rootsi määratud vastamistähtajast ootame 17. oktoobriks 2022 põhjendatud arvamusi
selle kohta, kas Eesti peaks osalema kõnealuse projekti piiriülese keskkonnamõju hindamise
menetluses. Juhul, kui peate vajalikuks Eesti osalemist menetluses, on oodatud ka arvamused selle
kohta, milline oluline kahjulik piiriülene keskkonnamõju võiks Eestile kaasneda, et arendaja saaks
sellega arvestada keskkonnamõju hindamise materjalide koostamisel.
Lugupidamisega
(allkirjastatud digitaalselt)
Kerli Kiili
Välissuhete osakonna juhataja
asekantsleri ülesannetes
Lisa: Konsultatsioonidokument
Rainer Persidski, 626 2973
Nimi | K.p. | Δ | Viit | Tüüp | Org | Osapooled |
---|---|---|---|---|---|---|
Kiri | 29.11.2024 | 3 | 7.2-4/24/20491-1 | Sissetulev kiri | transpordiamet | Kliimaministeerium |
Kiri | 18.10.2022 | 776 | 8-5/22/22386-2 | Valjaminev kiri | transpordiamet | Keskkonnaministeerium |
Lõppdokument | 08.07.2022 | 878 | 7.2-4/22/13272-2 | Valjaminev kiri | transpordiamet | Keskkonnaministeerium |
Projekti piiriülene keskkonnamõju hindamine | 14.06.2022 | 902 | 7.2-4/22/13272-1 | Sissetulev kiri | transpordiamet | Keskkonnaministeerium |